Your in depth explanation is so fabulous. Please make one play list of LE-TRA. I believe you will make a outstanding video on it. Cover the topics starting from creating transportation planning point, transportation zone, route, route determination, shipment document, shipment cost document. Then after transferring cost document how service entry sheet and PO will be created automatically. Please do a series on this.
@@Yours-Yuga-SAP-SD Hi Sir, I have maintained a pick pack time 2 days Loading time 2 RLT time 5 But I have created a sales order with no stock material. The system confirmed date is 11.06.2024. why Actually system will propose date is 18.06.2024 I have created a sales order with stock material the system confirmed date is today 08.06.2024 why
Hi ji, you have mentioned if stock is available then system considers pick/pack time or TLT whichever is higher.while calculating the dare fir 2nd line item why do we consider loading time also?
Hello thank you very much for your videos . I want to take the sd s4 Hana exam and have a question with traps : Which time components are used to calculate the confirmed delivery date in a sales order? Note: There are 2 correct answers to this question. A- Loading time of the shipping point B- Transit time of the route C- Transportation lead time of the forwarding agent D- Pick/pack time of the warehouse number Can help me please ?
Delivery date - transit = PGI PGI -loading = loading date loading date - TLT = Transport scheduled date loading date- pick pack = material availability date
Hi ji i have created one sale order , stock is also available, today i have created the sale order, delivery date is 11th , P&P 3 and Loading time 3, as per my order system is accepting back order, but it should be fail right, backward schedule, need to come forward schedule why system is accepting back order ?
HI JI We have punched the order on 10th jan , but customer delivery date is 13th jan, stock is also available , P&P 3 days, loading time 2 days, here backward is failed, now it goes to foward schedule , order punched on 10th jan 3 days P&P, 2 days loading time then here propose delivery date is 15th jan, customer delivery date 13th jan, even we have stock we cant able to delivery on 13 th jan, it will delivery on 15th jan, company need to support always customer requirement, in this situation how to delivery the goods on customer delivery date on 13th jan.
Hi Sir, Hi Sir, I have maintained a pick pack time - 2 days Loading time - 2 Days RLT time - 5 Days But I have created a sales order with no stock material. The system confirmed date is 11.06.2024. why ..? ( Actually system will propose date is 18.06.2024) I have created a sales order with stock material the system confirmed date is today 08.06.2024
Very helpful video, thank you!
THNAK YOU SIR VERY MUCH
CLEARED MY CONCEPTS
You are welcome
Nice explanation thank you for clear explanation
You are welcome
Your in depth explanation is so fabulous. Please make one play list of LE-TRA. I believe you will make a outstanding video on it. Cover the topics starting from creating transportation planning point, transportation zone, route, route determination, shipment document, shipment cost document. Then after transferring cost document how service entry sheet and PO will be created automatically. Please do a series on this.
Will try
Superb video bhai. Too good.
@@chetanbarokar you are welcome
Very helpful, keep it up
Thank you and you are welcome
Loading time and pick/pack time not consider only replenishment lead time consider. I did every setting what mentioned in videos
Check the document level and video, I mentioned one point, if stock is there which will consider, if stock is not there which one will consider
other scenario if stock is available PP or TLT, why you considering for TLT with transit time and loading time
Same as previous answer
Hi Sir,
Stock Material Have you maintained RLT time in material master?
Yes
@@Yours-Yuga-SAP-SD
Hi Sir,
I have maintained a pick pack time 2 days
Loading time 2
RLT time 5
But I have created a sales order with no stock material.
The system confirmed date is 11.06.2024. why
Actually system will propose date is 18.06.2024
I have created a sales order with stock material the system confirmed date is today 08.06.2024 why
Hi ji, you have mentioned if stock is available then system considers pick/pack time or TLT whichever is higher.while calculating the dare fir 2nd line item why do we consider loading time also?
Loading time we have to consider both cases, with stock or without stock
nice explanation
You are welcome
very nice video
Thank you
hi ji what happen if we are not set the loading time and pick & pack time in shipping point.
will system generate confirmed qty in schedule line.
Except that remaining It will consider if you not maintained in shipping point
Hi Sir,
Good Morning,
If i check without RLT Then what is the result in delivery scheduling?
For more detail about that watch the availability check video
If you check that , even if we don't have stock systems will confirm on future date
Hello thank you very much for your videos . I want to take the sd s4 Hana exam and have a question with traps : Which time components are used to calculate the confirmed delivery date in a sales order? Note: There are 2 correct answers to this question.
A- Loading time of the shipping point
B- Transit time of the route
C- Transportation lead time of the forwarding agent
D- Pick/pack time of the warehouse number
Can help me please ?
Delivery date - transit = PGI
PGI -loading = loading date
loading date - TLT = Transport scheduled date
loading date- pick pack = material availability date
Hi ji i have created one sale order , stock is also available, today i have created the sale order, delivery date is 11th , P&P 3 and Loading time 3, as per my order system is accepting back order, but it should be fail right, backward schedule, need to come forward schedule why system is accepting back order ?
Check your shipping point again it is matain or not and whether it was yours or not
Hi ji if stock not available you have given only (RLT + PP) why you considering loading time and transit time
That is the standard functionality, if business don't want that we will remove if they want we will add
@@Yours-Yuga-SAP-SD thanks a lot ji
HI JI We have punched the order on 10th jan , but customer delivery date is 13th jan, stock is also available , P&P 3 days, loading time 2 days, here backward is failed, now it goes to foward schedule , order punched on 10th jan 3 days P&P, 2 days loading time then here propose delivery date is 15th jan, customer delivery date 13th jan, even we have stock we cant able to delivery on 13 th jan, it will delivery on 15th jan,
company need to support always customer requirement, in this situation how to delivery the goods on customer delivery date on 13th jan.
@@sudhindrabn8154 that is the minimum for picking ,packing and lodging, so same we have to convey to customer we will dispatch on 15th
@@Yours-Yuga-SAP-SD thank you ji for your support
I AM CREATING SALES ORDER THEN ONLY CALCUATE RLT (9) DAYS NOT PICK , PACK TIME
I didn't get, can you please explain again
Hi Sir,
Hi Sir,
I have maintained a pick pack time - 2 days
Loading time - 2 Days
RLT time - 5 Days
But I have created a sales order with no stock material.
The system confirmed date is 11.06.2024. why ..? ( Actually system will propose date is 18.06.2024)
I have created a sales order with stock material the system confirmed date is today 08.06.2024
No stock means RLT not required, check your factory calendar may be Saturday and Sunday holiday is there
@@Yours-Yuga-SAP-SD Sunday Holiday.Sir
bro can you send me delivery scheduling pdf
Attached in description
Hi Sir,
Good Morning,
If i check without RLT Then what is the result in delivery scheduling?
For more detail about that watch the availability check video
If you check that , even if we don't have stock systems will confirm on future date