Hanging gardens by EVDEkimi. Redevelopment status 06.08.24 🚧

Поділитися
Вставка
  • Опубліковано 7 жов 2024
  • Hi there! Two weeks have passed, and it's time to see the progress on the Hanging Gardens Villa by EVDEkimi since our last update.
    All properties FOR SALE, plans, financial indicators, redevelopment progress, client reviews, and much more can be found on our Instagram account @evde.kimi. Follow us!
    Consultation, property selection: WhatsApp +6281338549380 or Telegram +994555901496
    Completed by August 6:
    ✔️Interior walls finished and painted
    ✔️Exterior walls painting and finishing underway
    ✔️Air conditioners installed
    ✔️Terrazzo floors poured in all rooms
    ✔️Windows and doors installation in progress
    ✔️Rainwater drainage system completed
    Plans for the next two weeks:
    📌Finish the terrazzo treatment of the pool
    📌Prepare for appliance installation
    📌Install furniture in the kitchen and bedrooms
    📌Add decorative elements and lighting in the courtyard
    📌Set up the water tank and pump
    We're staying on track, with project completion planned for the 3rd quarter of 2024.
    Follow us for more updates and watch the transformation unfold! Subscribe so you don't miss out on the latest news and exclusive content.