Metro Manila Skyway Stage 3 update as of January 2018

Поділитися
Вставка
  • Опубліковано 16 жов 2024
  • Happy New Year Everyone! This is my update #47 for my Metro Manila Skyway Stage 3 update series.
    As of January 1, 2018 this is what i have documented for the skyway stage 3.
    Section 1 is really speeding up! Along the Osmena Highway stretch only the Buendia flyover area remains without girders, almost the entire stretch is covered already in darkness, guess no more sun shine. You can also see most piers have pipes installed already for rain water. The big massive steel girders are still placed along Pier 0 to 5 area and these are the ones that will be placed along the flyover area. Massive steel girders!!!! wow!
    There are progress along section 2 , as the plaza dilao - PCA area.
    Section 3 and 4 are also moving. More piers are being built along section 4.
    I have high hopes that by 4th quarter section 1 will be open to motorist - just a hunch not official :-) fingers crossed!
    happy new year everyone and thank you for watching my videos.
    Thank you for giving me permission to take some footage around pier 1 to 5 sir :-)
    #buildbuildbuild #metromanilaskywaystage3