Las vigas del centro se doblan...deberian de ser mas gruesas ya que reciben cargas de 2 trchos planos...mal calculo... o distancia de vigas principales muy largas
The pole barn PEMB or PEB can have a Kspan roll curved roof. If a building permit is needed and can be obtained. 10 seconds for a PEMB or PEB to collapse, shown in text books since 1993. How about 16 gauge being good enough for a strong roof if a Kspan?
Las vigas del centro se doblan...deberian de ser mas gruesas ya que reciben cargas de 2 trchos planos...mal calculo... o distancia de vigas principales muy largas
Grab the cutting torches boys!
Niiiiiice, I hate it when I forget to install the braces!!! LOL at least nobody was injured. try again next time
Obviously no experience in erecting these structures.
😲 great indanger
Bracing issue.
The pole barn PEMB or PEB can have a Kspan roll curved roof. If a building permit is needed and can be obtained.
10 seconds for a PEMB or PEB to collapse, shown in text books since 1993. How about 16 gauge being good enough for a strong roof if a Kspan?
where did it collapsed?? and which company's material it was??
its in perundurai
I don't see any X brace and Tie beam
No bracing.
Whre did it collapsed...
there's not a single braced bay .... !!!
That's what I noticed ..no x braces installed as they erect
I heard a mexican that says it all
Diagonal braces
When you do not level
Superintendent reporting to the owner…. “How can I explain you….. this will take a little bit more time than you expected…. “😅😅
She was talking to you
Cowboy work
Where are the fucking bracing
Braces-!! 🤣🤣🤣
Sounds like the bolts were snapping. The steel seemed to hold up. Probably got the wrong bolts.