if we are using same calendar for task and resource dependant activity so not affecting the schedule but its affecting only when we are using different calendar for task dependant and resource dependant activity. so what is the use of task dependant and resource depandant activity its only dependant on calendar.
The resource-dependent activity type is for tasks that are controlled by resources. for instance, if you want to install three chillers on the roof of three buildings, but only one crane is available on the site, then the duration of the task depends on the availability of resources! If the resource isn't working (for other reasons), then we can't complete the task in time! The right choice for this task type is Resource Dependent!
Thanks to you Mr. Ahmad.
Thank you.
THANKS YOU
if we are using same calendar for task and resource dependant activity so not affecting the schedule but its affecting only when we are using different calendar for task dependant and resource dependant activity. so what is the use of task dependant and resource depandant activity its only dependant on calendar.
The resource-dependent activity type is for tasks that are controlled by resources. for instance, if you want to install three chillers on the roof of three buildings, but only one crane is available on the site, then the duration of the task depends on the availability of resources! If the resource isn't working (for other reasons), then we can't complete the task in time! The right choice for this task type is Resource Dependent!
🙏🙏👍
🙏🙏
i dont understand well