SAP MM- Release Procedure for Purchase Requestion(PR)- Full Overview for Beginners
Вставка
- Опубліковано 18 жов 2019
- Release procedure process explanation for PR, Explained clearly about characteristics/class/groups.
For Theory point view- Please visit Blog- Studyuuu.com
Thanq so much ramu garu for your support to people like me who can't afford to learn it's very much valuable to my career
Your welcome
THANK YOU SO MUCH SIR FOR SUCH GOOD AND CLEARLY EXPLANANTION ......THOSE 30MIN ARE WORTH IT
Your welcome
Thank You Sir for providing such a great job and ur teaching level is too good n useful.🙏
Thank you so much for the explanation Sir !!!
Useful video. I tried it is working fine
thank you sir, thank you so much for teaching the stratergy so well..... 😊😊
Your welcome
Very clear explanation
Thank you sir
Thankyou so much good explanation
Thank you sir.
Useful video. I tried it is working fine.
Great, thank you
Sir,,,is CL24N code is not required to assign the class with the release strategy created in PR release
How did you configure less than and greater than the amount price filed ?
Super explaination sir🙏🏾
Thank you
Sir... I'm getting error.. Please check release classes (see long text?
Hi ram
I have doubt on PR release procedure.in case of service/indirect procurement single level release is maintained, department heads will be approvers.consider a plant have 10departments and each cost center for each dept.
* now while defining release procedure is it sufficient to define only one release code so that basis consultants will give Authorization to all those department heads for that release code based on different cost center maintained in release strategy.(approvers should only be authorised for their cost center)
* or is it require to maintain 10release codes, each one for each department heads
One release code, mainly one thing u will be having respective approves for plants /pgroup (Eg) not through departments
Thank you
Thanks for the guidance.
You”r welcome
Can you explain without classification pr release process
But Y Srinivas, I never used those configuration even no company is using that
@@StudyuuuSAP-MM-EWM yesterday I attended one interview that interviewer asked sir, that's why I asked you sir,
@@srinivasjs Just tell you didn't configured those procedure
Sir, the release strategy option is not triggering while creating PR. What should I do?
I think u need to check the overall release check in release group and doc type configuration
Normally I will be doing these 2 mistakes
If not please share the screenshots, I’ll check
Sir it will get error PR 10000281 NOT SUBEJCT TO A RELEASE STRATEGY WHEN I enter multiple vendors
But when I only one plant define it will no error
It will not trigger generally
hello sir , can u help me with the topic shelf life-batch management
Ok
But mean while u have other videos in youtube
I'll upload that video soon
Hello Ram,
If a PR contains 2 line items. Is it possible to have different release strategies for those 2 items ?
I believe release strategy defined for the whole PR, not for the individual item but just wanted to confirm.
Thanks
Whenever u get these kind of doubts, think for business requirement , it will resolve automatically
In PR is release both item and header level also its possible 2 line items.
Sir whats the meaning of header level & Item level??? for 1item pr we consider item level or what??? or for multiple item PR we consider header lever or what??? Sir kindly clarify me
Thanks & Regards
Arya
Hello, Normally PR will go for item level because PR can be created with Multiple vendors but not PO, that’s the reason we can call as header and item
Is pricing is the only reason to use release strategy? What and all the causes/characteristics to use release procedure in real time?
Normally price and also u will use Versions also
Hi, in the release strategy you said will explain about 10, but explanation seems to be missed!!
It’s a strategy
Normally if you have 3 strategies then u can have 10/20/30
This is upto you
Sir,
what does release strategy code 10 means ??
It's a strategy that works on set of conditions
Hi Sir, Ur explanations are always good..but i suggest one thing..please be more confident and louder while explaining,,so u will get more likes & appreciation..apart from that ur SAP videos are great..I can understand easily any process through ur videos..
Thank you for your suggestion Saritha
Will do that for sure
@@StudyuuuSAP-MM-EWM best wishes..
Thank you
Sir, my doubt is that in release stratergy you used 10 and wrote price less 100. why u used 10? and why u didn't mention numerically less than 100??
I used 10 because I maintained strategy like 10 and 20 - that’s up to your wish
Coming to price- system understand decimals and specials characters but not alphabets
@@StudyuuuSAP-MM-EWM Can you explain in detail why you used 10 in release strategy? I cannot understand your explanation here.
It’s just a strategy Ramya
Nothing specific, u can use 10,20,30,40
I tried many times same process but not working.
I can't understand why it willnot work. I did same steps
Please send the screenshots of all configurations to studyuuusapmm@gmail.com
I’ll look into that and provide solution
@@StudyuuuSAP-MM-EWM
I created the "VL1" plant and did the release strategy with the same plant.
I doubt my plant with the letters, is it a mandatory plant in numbers?
Take some existing plant and try it if you have doubt
@@StudyuuuSAP-MM-EWM
Okay sir! Thank you for time and response. I will try once once again.
Sir, I watch every video in your UA-cam channel. Your explanation is very good. But we want SAP videos on support and Rollout project explanations and SAP support project details.
Request you to please do videos on it sir.
Sure
This topic release strategy is bit confusing
Listen once more, it's very easy
@@StudyuuuSAP-MM-EWM yes brother..actually at first i got confused..but when i watched the session again and again, it got eassier for me to understand..
Once again Thank you very much for your valuable sessions like this..
Thank you 👍👍
Sir you didn't tell why you gave 10 in release strategy?
It's just sequence
If you have 2 -3 strategies then 10/20/30