Thanks for the feedback and Compliment. We are glad to hear that our content has been helpful to our friends and viewers. We appreciate the feedback, please share our content on LinkedIn and other social media platforms with others. Remember to mention @planningp6 and #planningp6
Understood. But after the Look ahead is set, shouldn’t the Duration of the Summary activity be equal to the time set for the Look ahead.Guess am understood For instance , if the Look a head is a Four week look ahead, from the Data Date, the Summary of the Look ahead should be Four Weeks
Please visit the link: planningp6.com/how-to-create-3-month-lookback-in-primavera-p6-and-how-to-use-filters-to-create-a-3-month-lookback-in-primavera-p6/
Yes, it will also reflect the ongoing activities. To filter them as well, you'll need to either modify the lookahead filter or apply the global change option.
Excellent !
Your compliment is appreciated.
great,👍👍👍👍
Thanks
Thanks for the feedback and Compliment.
We are glad to hear that our content has been helpful to our friends and viewers. We appreciate the feedback, please share our content on LinkedIn and other social media platforms with others.
Remember to mention @planningp6 and #planningp6
Does it mean anytime your change your data date and schedule your program , your look ahead schedule changes?
Indeed, once the Data Date is modified, the look-ahead plan will also be updated.
Does it then change previous filters that had been done and saved?
Understood. But after the Look ahead is set, shouldn’t the Duration of the Summary activity be equal to the time set for the Look ahead.Guess am understood
For instance , if the Look a head is a Four week look ahead, from the Data Date, the Summary of the Look ahead should be Four Weeks
No, it isn't necessary.
That the overall duration should match the lookahead period at the summary level.
HOW DO YOU CREATE A 3 MONTH LOOKBACK
Please visit the link: planningp6.com/how-to-create-3-month-lookback-in-primavera-p6-and-how-to-use-filters-to-create-a-3-month-lookback-in-primavera-p6/
why in my primavera, there is no Global 2 weeks ahead, Milestone variation Baseline and Variance from Baseline?
Please add a new and modify as you want, after modifying make it Global.
👍👍👍
Sir,
does it also shows the activities which are in progress?
Yes, it will also reflect the ongoing activities.
To filter them as well, you'll need to either modify the lookahead filter or apply the global change option.