Advanced dependencies in Project for the web
Вставка
- Опубліковано 23 лип 2024
- First video of 2023! And with a bunch of really great additions to Project for the web.
👉 Watch next - • How to Project for the... Video 100, How to Project for the Web
Keep in mind that content I show on the video's is mostly available to you if you subscribe to the newsletter: eepurl.com/dsm7dj
00:00 New inhancements in Project for the web
02:34 Advanced dependencies in Project for the web
04:12 Dependencies from Microsoft Project
06:20 Other additions to Project for the web
08:24 Conditional Coloring
11:33 one thousand tasks limit
12:25 Custom Calendars in Project for the web
On The Project Corner Vlog you will find video’s about Project and Power BI. At times I’ll take sidesteps to Ms Teams, Power BI and the Power Platform. Have a look at the channel, there are topic specific Playlists available as well: / theprojectcornervlog
Subscribe to the channel by hitting the link below, new video’s every other week!
bit.ly/TPC_Subscribe
Link to related videos and playlists:
Project for the web monthly updates
• Project for the web mo...
Other links:
December update
techcommunity.microsoft.com/t...
January update
techcommunity.microsoft.com/t...
Custom vorking calendars
techcommunity.microsoft.com/t...
Very good news. Thanks for sharing. Still waiting for the baseline coming up in Project for the web soon.
You and me both! Baselines would be lovely to get in the tool.
It’s about time!
Agree, it's nice to have the feature now. Another great feature is here as well. Video inbound...
Hi there, to your knowledge is there any ways to link task between different project for the web?
I am at a loss at the moment and my 2 avenues are to write as a note the ID of the task in another project for the web and use power automate to sync them but thats limited to 1 task and also quite extensive... We could also go the oneplan route, sync to project online and master project from there, but again aaaa lot of work + 2 subscription
Hi chief, currently not an option sadly. But there are rumours about a program/portfolio layer coming. As soon as I see it I'll let you know. Thanks for commenting
For now ill be creating a display with powerapps to mimic "to-do list" cross projects and add the link to the line itself in it to facilitate cross projects updates. This will enable us to focus dependable task in one project even if it is suboptimal for now!
@@TheProjectCorner Actually went from powerautomate, composed a 2 variable array to filter for the "donor" and "receiver" of dates and went from there for now
Is there any way to start a task as late as possible in P4W? Thanks
Currently, no. But maybe this will be added to the tool later
They just rolled out the ability to add lead/lag to task.
Yessir, looking at the chance to do a video on the topic. It's a nice addition to the product.