10 More PMP Questions and Answers - PMBOK 7th Edition (41 to 50)

Поділитися
Вставка
  • Опубліковано 29 чер 2024
  • ⭐️⭐️⭐️ Get 35 Contact Hours / PDUs and 500 PMP Practice Questions in my Udemy course: www.udemy.com/course/ultimate...
    ✅ Or Get 52 ready-made Excel and PowerPoint project templates here: www.etsy.com/au/listing/11998...
    To kick-start your career once you pass the exam 🙂
    10 More scenario-based PMP Questions and Answers, from the latest PMBOK 7th Edition. Perfect preparation to pass your exam!
    Timestamps:
    00:00 Intro
    00:31 Question 41: Reduce project schedule
    02:55 Question 42: Project is behind
    05:26 Question 43: Schedule on an Agile project
    08:03 Question 44: WBS in an Agile project
    11:17 Question 45: Project missing scope
    14:39 Question 46: Creating an Agile team
    17:22 Question 47: System not used before
    19:59 Question 48: Creating communication plan
    22:19 Question 49: Materials delayed
    24:50 Question 50: Significant change to scope
    27:14 I truly believe in you. You can do it!
    #PMP #PMBOK #projectmanagement

КОМЕНТАРІ • 56

  • @raquell1212
    @raquell1212 Місяць тому +6

    Helpful tip: For schedule crashing remember "If you have CASH you can CRASH" hope this helps!!!

  • @lizpalvarez
    @lizpalvarez Рік тому +10

    Im taking the PM Exam on Wednesday, and I have to say, I feel very confident after watching your videos. Thank you very much for this content. For us visual learners, this was very helpful.

    • @msariel23
      @msariel23 5 місяців тому +3

      How did it go?

  • @satmurthi5239
    @satmurthi5239 Рік тому +12

    Appreciate your contribution David. I like the way you answer the questions just like we all do. It is natural. Also unlike others you don’t seek likes or subscriptions! Love the quality and high standards. Thank you

  • @louisakabobah1356
    @louisakabobah1356 11 місяців тому +3

    Hi @David. I took my PMP exams today and passed with 3ATs. Thanks so much for your videos. Incredibly helpful and practical.

  • @teojamie8450
    @teojamie8450 Рік тому +7

    Hi David, thank you for your online course. By also learning through your UA-cam channel, i passed my PMP exam and become PMP certified. Thank you.

  • @scottmoorby3176
    @scottmoorby3176 Рік тому +5

    While frustratingly disagreeable, these videos are incredibly helpful and I really appreciate the time you put into walking through the logic behind your answers. I legitimately cannot believe you went 50 for 50. I think I'm prepared for the exam but I'll probably still watch the 150 Questions video just to see if you finally get one wrong lol

    • @davidmclachlanproject
      @davidmclachlanproject  Рік тому +6

      Thank you for watching! I get caught out in the waterfall / process groups question set (100 Qs) 🙂

  • @brianszabos5358
    @brianszabos5358 9 місяців тому +1

    David - thank you so much for this series! Your informative style and thoughtful explanations make these videos extremely high value. The time spent viewing them and considering the questions is so worth it! I used this series to finalize my preparation. It gave me the confidence I needed to take on the PMP exam and pass it this week.

  • @burnerphone-de4lh
    @burnerphone-de4lh Рік тому +1

    What amazing resources! Thanks mate.

  • @anandts6973
    @anandts6973 Рік тому +3

    thansk for the videos david, helping me a lot, sincere Regards

  • @mahmoudatwa3564
    @mahmoudatwa3564 Рік тому +1

    excellent video, thanks a lot David!

  • @4chankrozb
    @4chankrozb Рік тому +1

    You are charismatic and I love your voice. Thanks for video

  • @semnaresh8339
    @semnaresh8339 Рік тому +2

    Quite tricky, i’m definitely learning. one day will come in my life i will also say proudly, I’m pmp certified. Thanks David🙏

  • @lynne2958
    @lynne2958 Рік тому +2

    Thank you for these videos, they've all been very helpful and were definitely a factor in my passing my PMP exam yesterday. Thank you!

    • @davidmclachlanproject
      @davidmclachlanproject  Рік тому +3

      Congratulations on passing your exam! 🙂

    • @lynne2958
      @lynne2958 Рік тому +1

      @@davidmclachlanproject thank you so much! You're awesome!

  • @ameerudinkkqaimkhani5340
    @ameerudinkkqaimkhani5340 12 днів тому

    Really helpful! Qs 9 shouldn’t we use procurement plan instead of resource plan for purchasing materials from outside country. Kindly explain. Thanks a lot for great services.

  • @MisterStubstep
    @MisterStubstep Рік тому +2

    Thank you as always

  • @ianazura7915
    @ianazura7915 Рік тому +1

    If this is your instructor .. your confidence raises by 1000 percent.. easy to understand with basic reasoning ...

  • @roberthochmut9577
    @roberthochmut9577 Рік тому +1

    Super good!

  • @gozdegoncer4458
    @gozdegoncer4458 Рік тому +1

    Hi David, thank you so so so much for your effort. I passed the exam with 3AT! Thanks againnn😊😊😊

  • @M.Ss8206
    @M.Ss8206 Рік тому

    david thanks for effort asking about new content outline exame

  • @justin9605
    @justin9605 6 місяців тому +1

    Thank you.

  • @fademi_jacobs
    @fademi_jacobs Місяць тому +1

    Cost baseline is the word you were looking for … in Q45

  • @abdelrahmanelsherbiny8833
    @abdelrahmanelsherbiny8833 7 місяців тому

    Great video

  • @snehalis.9235
    @snehalis.9235 3 місяці тому

    Much informative video

  • @brahmiimen3804
    @brahmiimen3804 5 місяців тому

    thank you

  • @scottmoorby3176
    @scottmoorby3176 Рік тому +1

    Regarding Q50, why on earth would you not take at least a quick look at the change control process before starting work on a significant scope change? Are we to assume there is no change control process in an agile project? Or is the question supposed to imply that the scope change is already approved? Your logic seems to be that we would want to review that change management plan but we would want to "do something else first," namely beginning work, and that makes no sense to me.

    • @davidmclachlanproject
      @davidmclachlanproject  Рік тому +3

      Great question. I guess this is the difference between a normal sequential project and an agile project. On an agile project, changes to "scope" (often shown as small, usable features) are most often controlled by the Product Owner. They don't need approval - they can reprioritize the feature list at any time. If we don't have a PO, the customer, Agile lead or PM could fill that role. I probably could have worded it better and included a PO in the question 🙂

    • @fabioloyola4788
      @fabioloyola4788 8 місяців тому

      @@davidmclachlanproject - Agreed, I think to add the PO would help. Although my concern about this question is that the "project will not deliver the aligned/initial benefits". This means I felt the need to see an answer that before an action has been taken, the stakeholders would become aware of the new scope and new benefits. I didn't feel right the team starts working in the new backlog without alignment with stakeholders (there is no indication that the PO or the PM got this direction/approval from the stakeholders to do something after the realisation of the "significant change in the scope"). I am not saying a rigid CCB but I don't think is right to start changing a lot the product backlog, without meeting stakeholders to review Agile Project Charter, Project and Product vision/objectives, release plan, product roadmap, benefits expectation and then agree a new series of iterations (if need to change them too). Thanks.

  • @jfrd101
    @jfrd101 Рік тому

    Q41 states that no further money can be spent, but we are adding more people, overtime or paying to expidite?

    • @davidmclachlanproject
      @davidmclachlanproject  Рік тому +1

      Schedule fast tracking is the answer for that one, and that is performing some activities in parallel (at the same time) instead of in sequence (no extra money required).
      Schedule crashing is adding money and resources 🙂

  • @Exploringwithmahsa
    @Exploringwithmahsa 3 місяці тому

    Hi guys, I don’t know why I can’t find the reference based on the page number he decreed in video, for example p59 means page 59? But in my pmbok edition seven page 59 is different!

  • @abosedebozimo3214
    @abosedebozimo3214 Рік тому

    I am a bit confused at the answer to the last question as I thought it was only the product owner that can prioritize the backlog.

  • @abdimaalik8627
    @abdimaalik8627 Рік тому

    Hi David, Thanks for your effort you really did good work, but am asking you about I was practiced your questions and i make self assessment, my result become like :
    1. 200 Agile i got 79% correct…
    2. 100 waterfall 74% correct..
    3. 150 PMBOK 7 65% Correct..
    Kindly Am i ready to take PMP Exam or need improvement, whats your advice based on my result…
    Looking forward to be hearing from you. thanks

    • @davidmclachlanproject
      @davidmclachlanproject  Рік тому +2

      You are doing great! I would do a quick refresher of the PMBOK 7 questions and try and get it up a bit. It covers the mindset that you need. Watch it at 1.5 speed if that helps 😄

  • @surajdharmoje9488
    @surajdharmoje9488 11 місяців тому

    For Q46 - Since the Project Manager is still in the Planning stage I think the answer to this question can't be D as this talks about "Acquiring Project resources " which actually falls under execution phase!! can someone check and comment on this?

    • @mauropirri2935
      @mauropirri2935 8 місяців тому

      I had exactly the same doubts. Also before selecting the small team, I truly believe that the PM has to be aware of the required resources and this is possible only after having finalized the Resource Management Plan. Any expert can give us his opinion?

    • @mn1103mn
      @mn1103mn 5 місяців тому

      EXACTLY! I was searching through comments if anyone else commented on answer 46! since when colocation was the number one priority in agile teams!??@@mauropirri2935 @surajdharmoje9488

  • @catherinedouglas9845
    @catherinedouglas9845 Рік тому

    Sir, Please help me. I want to write the PMP exam fear is not my friend. How can I contact you? Too many persons I know fail the it on their first attempt this has caused me to develop a learning block. Instead of concentrating on learning the material I am worried about failing….the humiliation part is affecting me greatly

    • @davidmclachlanproject
      @davidmclachlanproject  Рік тому +3

      You can do this. I know you can do this. I am a C student - a failure for many years in most cases, and yet with persistence and dedication I managed to pass the PMP exam, and others. That means you can do it too. It will take hard work, and you have to put in the time every day.
      Review my 200 Agile Questions video and the 150 PMBOK 7 questions video, or take as many practice exams as you can.
      One secret I used was "NET" time - "No Extra Time" - where I would study by watching videos or listening to them (often on Udemy or UA-cam) while doing something else, like taking the train to work, cooking dinner or exercising. If you don't have time, do two things at once.
      Keep going. I believe in you!

    • @catherinedouglas9845
      @catherinedouglas9845 Рік тому +2

      @@davidmclachlanproject thank you Sir. Those videos you mentioned are already bookmarked. I am going thru the questions and I am getting a better understanding based on ur explanations. I will give u an update at the end of January and depending on how I feel I will submit my application to PMI in February and hopefully by march I can write the exam. I will keep in touch Sir. Thanks for responding and the words of encouragement. Gona push even harder now

  • @xxchuangtzu6186
    @xxchuangtzu6186 Рік тому

    Question 45: Unclear wording. If the project is having a “current progress” review it has already started with an approved scope. If a need for a substantial change (for a “critical piece”) is then noted by the sponsor, the scope must be changed. The CCB must approve this. Management reserves are for unforeseen changes. Why would contingency reserves not be used?

    • @scottmoorby3176
      @scottmoorby3176 Рік тому

      David explains that the sponsor is part of CCB and can be assumed to be approving on their behalf. Contingency reserves are for risks that are foreseen at the outset of the project. There was no money specifically set aside for this issue at the outset of the project, since it was suddenly discovered later in the project, so management reserves are applicable here.

    • @scottmoorby3176
      @scottmoorby3176 Рік тому

      But also, yes, many of these questions are frustratingly unclear in their wording and many of the answers require certain assumptions that cannot be explicitly determined from the questions. If I fail the exam because of some BS like that I'm gonna lose it.

  • @xxchuangtzu6186
    @xxchuangtzu6186 Рік тому

    Question 45: "source part of your team externally if they have skillsets in the new system". Not clear to whom :"they" refers. Reword for clarity, please.

  • @scottmoorby3176
    @scottmoorby3176 Рік тому +1

    I don't see how the answer to Q44 satisfies the business analysts in any way.

    • @davidmclachlanproject
      @davidmclachlanproject  Рік тому +1

      For that one, it's more the difference between planning for an agile project, and planning for a predictive/sequential project. The key difference is we won't do it all at once, we'll use "Rolling wave planning" and break down & estimate the nearest scope first, then do that continuously as the project goes on.