Yes, Er. Hany, Always a Planning Engineer shall have a good relationship with the project team. To be frank not all the time the Construction team is so happy to see Planning Engineer since we ask all the updates. So a very good relationship is must. Even similar nationality, similar language will play a major role. However we can’t always expect to be people from same country or language. So good relationship is must irrespective of any criteria. Even No harm discussing productivity with Site Foremen and Technicians.
Hi Sir. Thanks in advance. Have one doubt . How can I change the calendar for example : if i have to put every 2 nd Saturday off and 4th Thursday half day to all activities if there are more than 1000 activities
Yes, Er. Hany, Always a Planning Engineer shall have a good relationship with the project team. To be frank not all the time the Construction team is so happy to see Planning Engineer since we ask all the updates. So a very good relationship is must. Even similar nationality, similar language will play a major role. However we can’t always expect to be people from same country or language. So good relationship is must irrespective of any criteria. Even No harm discussing productivity with Site Foremen and Technicians.
Mr. Hany Please solve this issue--->>Budgeted Cost recalculates to zero when Original Duration changes
please explaine some work ( substructures )
What happens when you discover another risk when the project is ongoing? What do you do?
Hi Sir. Thanks in advance.
Have one doubt . How can I change the calendar for example : if i have to put every 2 nd Saturday off and 4th Thursday half day to all activities if there are more than 1000 activities
how to make page setup for original which has become default
I do thank you very much indeed
May your good self add the link to that course please
You are most welcome. My courses are available on this link: planningengineer.net/lp-courses/
Happy Eid Al Adha
Can you return back the discount over courses please
Thanks a lot