Aoa sir main saudi azad visa pe aya ho bachelor kiya hai geology mai civil lab technician bhi raha ho 2 years pakistan main yaha 1 month se ho konsa job sahi rahega sab aramco approved mangte hai koi advise doge tu mehrobani hogi
"Welcome to KSA, brother! There are numerous opportunities for lab technicians in non-Aramco projects as well. Prepare yourself with updated standards and specifications. Search for jobs on expatriates. Join some WhatsApp groups with the help of your friends, and seek advice from them. Insha Allah, you will secure a very good job."
after filling the rfi excel format from. where we have to submit rfi form whether its a separate app are there or through WhatsApp we have to submit rfi form for both aramco and non Aramco project?
@RizwanShaikh-by1rw once you're done with the inspection and everyone has signed off, you need to upload the RFI front page, ITP, checklists, drawings, and any other relevant documents to EPM/QMIS/Acconex. As for informing your team about the inspection schedule, each PID has their own preference. You can either share your daily RFI log via email or send them a list of scheduled activities on WhatsApp. Here's an example for you: *RFI SCHEDULE FOR 7TH AUGUST 2024* 1. Inspection Request - Cement Based Non-Shrink Grout (Sikadur-114) Surface Preparation & Formwork Installation for Seal plan 53B (X03-G--0118A,B) OWS 2. Inspection Request - Cement Based Non-Shrink Grout (Sikadur-114) Surface Preparation & Formwork Installation for Seal plan HRS 3. Inspection Request - Mixing, Placement, Sampling, Testing, Curing, and Final installation of Cement Based Non-Shrink Grout (Sikadur-114) for Seal plan
@RizwanShaikh-by1rw All inspection requests will be submitted as follows: At least twenty-four (24) hours prior to the time of the inspection for normal work hours (7:00 AM - 5:00 PM, Saturday through Thursday), or according to Client’s Schedule. Forty-eight (48) hours for weekend or holidays. Remote Areas: A minimum of 48 hours advance notice is required except when air travel is required. In this situation, a minimum of seven (7) days advance notification is required
after filling the rfi excel format from. where we have to submit rfi form whether its a separate app are there or through WhatsApp we have to submit rfi form for both aramco and non Aramco project?
after filling the rfi excel format from. where we have to submit rfi form whether its a separate app are there or through WhatsApp we have to submit rfi form for both aramco and non Aramco project?
Nice
wow em big fan sir ALLAH BLESSED U
Thank you for make it easy and simple..
You are welcome 😊
Thank you brother
excellent sir.g .i need it please share with me .i will will be very thankful sir
@@EngrAbdullah2252 what do you need?
Aoa sir main saudi azad visa pe aya ho bachelor kiya hai geology mai civil lab technician bhi raha ho 2 years pakistan main yaha 1 month se ho konsa job sahi rahega sab aramco approved mangte hai koi advise doge tu mehrobani hogi
"Welcome to KSA, brother! There are numerous opportunities for lab technicians in non-Aramco projects as well. Prepare yourself with updated standards and specifications. Search for jobs on expatriates. Join some WhatsApp groups with the help of your friends, and seek advice from them. Insha Allah, you will secure a very good job."
after filling the rfi excel format from. where we have to submit rfi form whether its a separate app are there or through WhatsApp we have to submit rfi form for both aramco and non Aramco project?
@RizwanShaikh-by1rw
once you're done with the inspection and everyone has signed off, you need to upload the RFI front page, ITP, checklists, drawings, and any other relevant documents to EPM/QMIS/Acconex.
As for informing your team about the inspection schedule, each PID has their own preference. You can either share your daily RFI log via email or send them a list of scheduled activities on WhatsApp.
Here's an example for you:
*RFI SCHEDULE FOR 7TH AUGUST 2024*
1. Inspection Request - Cement Based Non-Shrink Grout (Sikadur-114) Surface Preparation & Formwork Installation for Seal plan 53B (X03-G--0118A,B) OWS
2. Inspection Request - Cement Based Non-Shrink Grout (Sikadur-114) Surface Preparation & Formwork Installation for Seal plan HRS
3. Inspection Request - Mixing, Placement, Sampling, Testing, Curing, and Final installation of Cement Based Non-Shrink Grout (Sikadur-114) for Seal plan
How many hours before we have to submit rfi?
@RizwanShaikh-by1rw All inspection requests will be submitted as follows:
At least twenty-four (24) hours prior to the time of the inspection for normal work hours (7:00 AM - 5:00 PM, Saturday through Thursday), or according to Client’s Schedule.
Forty-eight (48) hours for weekend or holidays.
Remote Areas: A minimum of 48 hours advance notice is required except when air travel is required. In this situation, a minimum of seven (7) days advance notification is required
Sir aramco ki checklist share kr den discription mn .
Please reach us at 2iconstructionz@gmail.com.
📍📍📚📚📚📍📍
*SAUDI ARAMCO TYPICAL INSPECTION PLANS (For civil work)*
1 SATIP-A -000-01 Soil Improvement (Vibro Replacement & Vibro Compaction) CVL
2 SATIP-A-104-01 High Density Polyethylene (HDPE) Liner for Wastewater Disposal Evaporation Ponds CVL
3 SATIP-A-113-01 Geotechnical Investigation CVL
4 SATIP-A-114-01 Earthwork - Site Preparation, Excavation and Backfill During Construction CVL
5 SATIP-B-006-01 Fireproofing Concrete CVL
6 SATIP-H-003-01 Coating Application on Concrete Surfaces CVL
7 SATIP-L-450-01 On-Land and Near-Shore Pipelines CVL
8 SATIP-M-006-01 Security and General Purpose Fencing CVL
9 SATIP-M-100-01 Concrete Masonry Units and Building Bricks CVL
10 SATIP-M-100-02 Waterproofing of Roof Slabs CVL
11 SATIP-M-100-03 Structural Steel - For Buildings CVL
12 SATIP-M-100-04 Pre-Engineered Metal Buildings CVL
13 SATIP-M-100-05 Gypsum Board System Installation CVL
14 SATIP-M-100-06 Ceramic Wall and Floor Tiles CVL
15 SATIP-M-100-07 Doors and Windows CVL
16 SATIP-M-100-08 Acoustical False Ceiling System CVL
17 SATIP-M-100-09 Glass and Glazing CVL
18 SATIP-M-100-10 Resilient Vinyl Composition Floor Tile & Base CVL
19 SATIP-M-100-11 Raised Equipment Floors System CVL
20 SATIP-O-101-01 Security Fencing & Gates, (Type SSD1 Standard Security Fence) CVL
21 SATIP-Q-001-01 Ready Mix Concrete Batch Plants and 3rd Party Laboratory Management CVL
22 SATIP-Q-001-02 Cast-In-Place Portland Cement Concrete CVL
23 SATIP-Q-001-03 Pre-Cast Concrete Fence Posts at Fabrication Yards CVL
24 SATIP-Q-001-04 Structural Precast Prestressed Concrete at Fabrication Yards CVL
25 SATIP-Q-006-01 Conventional Asphalt & Sulfur Extended CVL
26 SATIP-Q-006-02 Conventional & Sulfur Extended Asphalt Paving CVL
27 SATIP-Q-006-03 Foamed Asphalt Stabilization CVL
28 SATIP-Q-010-01 Cement Based Non-Shrink Grouting CVL
29 SATIP-Q-011-01 Epoxy Grout For Machinery Support CVL
30 SATIP-Q-012-01 Installation of Structural and Architectural Pre-cast Concrete CVL
31 SATIP-S-070-01 Earthwork - Excavation and Backfill For Under Ground Utilities
🔴🔴
*SATIP-M-100-01 Concrete Masonry Units and Building Bricks CVL*
1 SAIC-M-1006 Concrete Masonry Unit (CMU) Compressive Strength and Aggregate Test Reports CVL
2 SAIC-M-1007 Masonry Materials Receiving and Storage Inspection CVL
3 SAIC-Q-1007 FBE Rebar & Embedments Receiving Inspection CVL
4 SAIC-M-1008 Concrete and CMU Surface Preparation and Protection Inspection CVL
5 SAIC-M-1009 Masonry Units and Plaster Installation Inspection CVL
🔴🔴
*SATIP-M-100-02 Waterproofing of Roof Slabs CVL*
1 SAIC-M-1012 Waterproofing Receiving and Storage Inspection CVL
2 SAIC-M-1014 Waterproofing Surface Preparation, Waterproofing Layer Installation Inspection final CVL
3 SAIC-M-1018 Waterproofing Final Inspection final CVL
4 SATR-M-1014 Roof Flood Testing CVL
🔴🔴
*SATIP-M-100-04 Pre-Engineered Metal Buildings CVL*
1 SAIC-M-1031 Pre-Engineered Building Components Material Receiving, Handling & Storage Inspection CVL
2 SAIC-M-1032 Pre-Engineered Building - Foundations and Pre-Installation Inspection CVL
3 SAIC-M-1033 Pre-Engineered Building - Components and Accessories Installation Inspection CVL
4 SAIC-M-1034 Pre-Engineered Buildings - Interior and Exterior Final Inspection CVL
🔴🔴
*SATIP-M-100-05 Gypsum Board System Installation CVL*
1 SAIC-M-1035 Gypsum Board System Receiving & Storage Inspection CVL
2 SAIC-M-1037 Gypsum Board Framing, Insulation, and Pre-Installation Inspection CVL
3 SAIC-M-1038 Gypsum Board Installation Inspection CVL
4 SAIC-M-1039 Gypsum Board System Plastering, Finishing and Final Inspection CVL
🔴🔴
*SATIP-M-100-06 Ceramic Wall and Floor Tiles CVL*
1 SAIC-M-1041 Ceramic Wall and Floor Tiles and Accessories Receiving and Storage Inspection CVL
2 SAIC-M-1043 Ceramic Wall and Floor Tile Pre-Installation and Surface Preparation Inspection CVL
3 SAIC-M-1044 Ceramic Wall and Floor Tiles Installation and Final Inspection CVL
🔴🔴
*SATIP-M-100-07 Doors and Windows CVL*
1 SAIC-M-1046 Metal Doors & Windows Receiving Inspection CVL
2 SAIC-M-1047 Metal Doors and Windows Pre-Installation Inspection CVL
3 SAIC-M-1049 Metal Doors and Windows Installation Inspection CVL
4 SAIC-M-1051 Metal Doors and Windows Final Inspection CVL
🔴🔴
*SATIP-M-100-08 Acoustical False Ceiling System CVL*
1 SAIC-M-1052 Acoustical False Ceilings Receiving & Storage Inspection CVL
2 SAIC-M-1053 Ceilings Suspension System Installation Inspection CVL
3 SAIC-M-1054 Acoustical False Ceilings Installation & Final Inspection CVL
4 SAIC-M-1055 Raised Equipment Floor Installation and Final Inspection CVL
🔴🔴
*SATIP-M-100-09 Glass and Glazing CVL*
1 SAIC-M-1057 Glass & Glazing Receiving and Storage Inspection CVL
2 SAIC-M-1059 Glass & Glazing Pre-Installation Inspection CVL
3 SAIC-M-1060 Glass & Glazing Installation & Final Inspection CVL
4 SATR-M-1060A Glass Window or Glass Curtain Wall Installation Leak Test Procedure and Form CVL
5 SATR-M-1060B Glass Window or Glass Curtain Wall Installation Tests and Warranties CVL
🔴🔴
*SATIP-M-100-10 Resilient Vinyl Composition Floor Tile & Base CVL*
1 SAIC-M-1062 Resilient Vinyl Floor Tile & Base Receiving & Storage Inspection CVL
2 SAIC-M-1063 Resilient Vinyl Floor Tile Pre - Installation inspection CVL
3 SATR-M-1063 Concrete Floor Moisture and pH Tests (For Resilent Vinyl Purposes) CVL
4 SAIC-M-1064 Resilient Vinyl Floor Tile Installation and Final Inspection CVL
🔴🔴
*SATIP-M-100-03 Structural Steel - For Buildings CVL*
1 SAIC-M-1065 Review of Procedure for Tightening of High Strength ASTM A325 and A490 Bolts CVL
2 SAIC-M-1066 Review of Procedure for Localized Heating to Correct Warping CVL
3 SAIC-M-1067 Receiving Inspection of Structural Steel Shapes & Plates CVL
4 SAIC-M-2021 Bolts, Nuts and Washers Receiving CVL
5 SAIC-M-2004 Fabricated Steel Structures Receiving CVL
6 SAIC-M-1068 Storage, Handling and Preservation of Structural Steel Materials and Components CVL
7 SAIC-M-1069 Inspection of Support Foundation Prior to Structural Installation CVL
8 SAIC-M-1070 Inspection Of Structural Alignment During Erection CVL
9 SATR-M 2001 10 SAIC-M-1071 Repair Correction of Errors of Structural Alignment CVL
11 SATR-M-2002 Pre-Installation Procedure Verification Testing of Turn-of-the-Nut Method (ASTM A325 or A490 Bolts) CVL
12 SATR-M-2003 Pre-Installation Procedure Verification Testing of Direct Tension Indicator (ASTM A325 or A490 Bolts) CVL
13 SATR-M-2004 Pre-Installation Procedure Verification Testing of Calibration Wrench (ASTM A325 or A490 Bolts) CVL
14 SAIC-M-1072 High Strength Bolts Tightening Inspection and Testing (ASTM A325 or A490 Bolts CVL
15 SAIC-M-1073 Inspection of Structure Installation CVL
16 SAIC-M-1074 Structural Re-instatement Punchlisting CVL
17 SATR-A 2011 Re-instatement Checklist (Form) or Punchlist Form CVL
🔴🔴
*SATIP-M-100-11 Raised Equipment Floors System CVL*
1 SAIC-M-1055 Raised Equipment Floor System nstallation and Final Inspection CVL
2 SAIC-M-1075 Raised Equipment Floor Material Receiving Inspection CVL
after filling the rfi excel format from. where we have to submit rfi form whether its a separate app are there or through WhatsApp we have to submit rfi form for both aramco and non Aramco project?
I hope it's clear now.
after filling the rfi excel format from. where we have to submit rfi form whether its a separate app are there or through WhatsApp we have to submit rfi form for both aramco and non Aramco project?
Already responded