MS Pipe Laying all process like - ROU/ROW clear, Alignment marking, Grading, Excavation, Pipe dump.

Поділитися
Вставка
  • Опубліковано 5 вер 2024
  • How to laying all process like- First talk with farmers & convence them For pipe laying in His land. we have to give them Crops Compensation then clear ROU/Row after then we have to find out where is our line alignment here We use DGPS instrument For finding alignment after then mark on line to white chuna then Excavation with the help of Excavator them sand bidding then welding pit then dump pipe in trench then Granding end of both pipe then pipe fitting Rout gaps will be 3.15 mm to 4 mm then welding process start outer and inner after then sand blast on joint them coating process start. pend, slive