  • MORTH Section 500
    Clause 505. Dense Bituminous Macadam
    The Specification describe the design and Construction procedure for Dense Bituminous Macadam (DBM), as a surface course material. laid on approved Primed surface of Base or sub-base. the thickness of DBM in single layer shall be 50 mm to 100 mm
    Material - Coarse Aggregate shall consist of crushed rock, crushed gravel or other Hard material retained on 2.36 mm sieve. The aggregate shall satisfy the requirements specified in MORTH section 500 table 500-8
    Filler shall consist of finely divided mineral matter such as rock dust, hydrated lime or cement. the filler shall be graded within the limits indicated in table 500-9
    Table 500-8 physical requirement for Coarse Aggregate for Dense Bituminous Macadam
    AIV - Max 27% as per IS2386 Part iv
    EI & FI - Max 35% as per IS 2386 part I
    Durability soundness either,
    Sodium sulphate 12% IS 2386 part v
    Magnesium Sulfate 18%
    Water absorption - Max. 2% IS 2386 part III
    Coating and striping of Bitumen aggregate mix Min. retained coating 95% IS 6241
    Water sensitivity Retained tensile strength
    Min. 80% AASHTO 283
    Table 500-9
    Grading requirements for Mineral Filler
    Table 500-10
    Composition of Dense graded Bituminous macadam
    Nominal Aggregate Size
    Grading 1 37.5
    IS sieve (mm) passing %
    45 100
    37.5. 95-100
    26.5. 63-93
    13.2. 55-75
    4.75. 38-54
    2.36. 28-42
    .300. 7-21
    .075. 2-8
    Bitumen content % by mass of total mix.
    Min. 4%
    MiX design as per Asphalt Institute Manual MS-2
    job mix formula DBM shall be prepare as per specification
    Laying and Rolling
    Laying temperature 150•c
    Rolling tempreture min. 100•c
    Mixing at HMP
    Bitumen Temperature 160•c-170•c
    Aggregate Temperature 160•c - 175•c
    Mixed Material Temperature 160-170•c
    Laying temperature min. 150•c
    Rolling Tempreture. Min. 100•c
    Bitumen used for mix is Viscus grade VG 40 as per IS: 73
    RS 1 is used as tack coat material as per IS 8887
    rate of spray of tack coat on primed surface before DBM laying is per table 500-5 is 0. 25 kg to 0. 30kg per square meter with the help of specified sprayer distributor with suitable nozzle
    Speed of Roller shall be 5km per hour during rolling of mix at site
    Rolling should be from edge to center or Lower to higher side.
    Mic - GoPro Media Mode amzn.in/d/8SYtIrG
    Camera - GoPro HERO9 amzn.in/d/adn1ka8
    Memory card - SanDisk Ultra 128GB microSDXC UHS-I, 140MB/s amzn.in/d/0nvjeXI
    Mobile phone - Apple iPhone 13 (128GB) - amzn.in/d/fRRDFcc
    Camping Tent - Decathlon Camping Tent amzn.in/d/bL9I04U
    Traveller Bag -TRAWOC 65 Liter amzn.in/d/6RLVqG6
    Filter water Bottle - Paany! Silicone Foldable Water Purifier Bottle (750ml, Black/White) amzn.in/d/ijuNYEx

КОМЕНТАРІ • 52

  • @hemanandasahu9460
    @hemanandasahu9460 4 місяці тому

    Very good explanation sir...

  • @user-gm4pc6vv4u
    @user-gm4pc6vv4u 2 місяці тому

    ❤❤❤❤❤

  • @Riasatmaseeh
    @Riasatmaseeh 5 місяців тому

    ❤❤❤❤

  • @visweswaraiahkonkallu6832
    @visweswaraiahkonkallu6832 4 місяці тому

    👍

  • @YogendraSingh-qt5kd
    @YogendraSingh-qt5kd 2 роки тому +2

    Very nice explanation.
    Interrupted voice due to sounded machines.

  • @bantimandrah8706
    @bantimandrah8706 3 роки тому +1

    Good Sharma ji keep it up 👌

  • @Sunitakumari-di2lj
    @Sunitakumari-di2lj 2 роки тому +1

    good job keep it up

  • @bandanakumari6106
    @bandanakumari6106 2 роки тому +1

    good explanation

  • @kanhayakumar2044
    @kanhayakumar2044 2 роки тому +1

    good job

  • @pratirajkumar8724
    @pratirajkumar8724 2 роки тому +1

    great effort

  • @prithasharma2584
    @prithasharma2584 2 роки тому +1

    Great job

  • @Dhirajkumar-po5dl
    @Dhirajkumar-po5dl 2 роки тому +1

    very well explained

  • @singhnandan80
    @singhnandan80 2 роки тому +1

    Nice

  • @infinii.
    @infinii. Рік тому

    Thank you sir

  • @palakbhardwaj9239
    @palakbhardwaj9239 2 роки тому +1

    nice

  • @ManojYadav-ew1kz
    @ManojYadav-ew1kz 4 місяці тому

    Hello ❤

  • @civiltechnoharyana7850
    @civiltechnoharyana7850 Рік тому

    Dbm laying mein jab lay karte h toh jo longitudinal joint bante h unko kaise overcome kare ya rectify kare ya kya process h ki joint na dikhe

    • @nomadprs
      @nomadprs  Рік тому

      Logitudnal joint ko carefully banana chahiye.ise banate samay vertical cut Kare phir minimum 50mm overlap laying Kare.Rolling kar sabse pahle longitudinal joint ko Compact kar le. workman ship ke liye achhe skilled laying labour hona chahiye. Straight edge ka upyog kar gap ko check kar le. is Tarah aapka longitudinal joint sahi banega

  • @ghostgamingyt3318
    @ghostgamingyt3318 6 місяців тому

    Hello bhaiya kahi Pever oprater me jagh hai toh batana

  • @SHARAT388
    @SHARAT388 2 роки тому

    Please share the morth literature...which states that loose thickenss should be 30 percent more than targeted compacted thickness

    • @nomadprs
      @nomadprs  2 роки тому +1

      about loose thickness of DBM it's all depend on trial and error method. MORTH say that Before start DBM laying you first prepare trail patch where you confirm compaction

  • @maheshwardeshmukh7485
    @maheshwardeshmukh7485 Рік тому

    Sir, under PMGSY Department on ongoing site where we have done wmm and applied Emulsion ss1 but when we do tackcoat and start for 20 mm thick OGPC carpet then the layer of mud sticks to tyre of vehicle, and the only dust remains on surface after that, we dont have provision of dbm and bc we only have to do wmm then prime coat then tackcoat then 20 mm carpet how to do plz reply

    • @nomadprs
      @nomadprs  Рік тому

      After the application of Prime coat SS1 the Primed surface shall be closed for 24 hour and after 24 hour tack coat RS1 you can use before laying of OGPC.

    • @pareeksha2182
      @pareeksha2182 9 місяців тому

      Some are road is very damaged for that can i use BM and for other pre-mix carpet with use of emulsion as tack coat. Further can we apply pre-mix carpet over BM ??

    • @nomadprs
      @nomadprs  9 місяців тому +1

      After BM you can use seal coat for better result

    • @nomadprs
      @nomadprs  9 місяців тому

      BM is best material for potholes filling and BM laying we can use Seal coat

    • @pareeksha2182
      @pareeksha2182 9 місяців тому

      @@nomadprs some portion of roads are in good condition but need resurfacing so can i use 2.5 cm pre-mix carpet item for that...

  • @sahiblaskar8593
    @sahiblaskar8593 7 місяців тому

    Bhi vdo app sahi lakin vdo ka quality nhi aara ha,,

    • @nomadprs
      @nomadprs  7 місяців тому

      Koshis karunga achha video Banaunga

  • @ratanlalnishad9650
    @ratanlalnishad9650 3 роки тому +1

    Dear Respected sir please used Bluetooth or Earphone for proper valume

  • @Civilhunt1234
    @Civilhunt1234 9 місяців тому

    sir rate of prime coat, tack coat, seal coat bataye

    • @nomadprs
      @nomadprs  9 місяців тому

      Prime coat @ 0.7 to 1kg/Sqm
      Tack coat @ 0.25kg to 0.3kg/sqm

    • @nomadprs
      @nomadprs  9 місяців тому

      Seal coat me Bitumin 6 to 7%

  • @akhileshverma9823
    @akhileshverma9823 2 роки тому

    Dust kitne percent h?? Pls rply

    • @nomadprs
      @nomadprs  2 роки тому +2

      depends on gradation of aggregate
      in our project dust percentage is 45 to 50 percent

    • @akhileshverma9823
      @akhileshverma9823 2 роки тому

      For DBM??

    • @nomadprs
      @nomadprs  2 роки тому +2

      Yes for DBM dust is 45 to 50%

  • @dilipchaturvedi3565
    @dilipchaturvedi3565 2 роки тому

    Aap 100 mm thickness ek hi baar me kar rahe hain

    • @nomadprs
      @nomadprs  2 роки тому +1

      as per morth section 500, 100 mm thickness of DBM laying is permissible

  • @ayazarmaania
    @ayazarmaania 2 роки тому

    Loose thickness kitna lena

    • @nomadprs
      @nomadprs  2 роки тому +1

      For Compacted 100mm Loose thickness 128 to 130mm

    • @ayazarmaania
      @ayazarmaania 2 роки тому

      @@nomadprs For compacted Bituminous concrete 30 mm k liye kitna loose thickness hoga.
      Aur Bituminous Macadam compacted 50 mm k liye kitna loose thickness hoga

    • @ayazarmaania
      @ayazarmaania 2 роки тому

      Pls reply

    • @ayazarmaania
      @ayazarmaania 2 роки тому

      BM grading2 and BC grading2 k liye loose thickness

    • @pareeksha2182
      @pareeksha2182 9 місяців тому

      ​@@ayazarmaania100 mm

  • @rajeevranjankumar5274
    @rajeevranjankumar5274 2 роки тому +1

    good job keep it up

  • @Himanshukumar-cr2re
    @Himanshukumar-cr2re 2 роки тому +1

    good job

  • @raghwendrasharma6571
    @raghwendrasharma6571 2 роки тому +1

    good job

  • @parthkumar7189
    @parthkumar7189 2 роки тому +1

    good job