Earned Value Management for Project Managers: EVM explained by an APM PMQ trainer

Поділитися
Вставка
  • Опубліковано 5 лис 2024

КОМЕНТАРІ • 19

  • @Dwavard
    @Dwavard 5 місяців тому

    We’ll done for explaining one of the toughest elements of the APM PM exam! Very useful 😀

  • @petemovements
    @petemovements Рік тому

    watching this let me understand this technique a little bit more, very well explained and at a good pace. Thank you.

  • @imransiddique3910
    @imransiddique3910 3 роки тому

    One of the best video on the EVM! Thank you so much

  • @curiousguy9544
    @curiousguy9544 2 роки тому

    brilliant. now i really understand what earned value management is all about.

  • @krtk77
    @krtk77 3 роки тому +2

    Very good explanation and simple. Thank you

  • @aseyeseait
    @aseyeseait 2 роки тому +5

    How did you work out you had 25% of wall?

    • @gc9522
      @gc9522 2 роки тому

      Confuses me too. Would make sense if the days were 20 but it was calculated at half not quarter.

    • @regian_77
      @regian_77 Рік тому

      EV=percent work completed(%) x planned cost=.50%x500=250

  • @Fatimalnx
    @Fatimalnx 3 роки тому

    Simple and effective! Thank you so much!

  • @craiggilbert6159
    @craiggilbert6159 Рік тому

    Great video indeed!!

  • @IOSauca
    @IOSauca 4 місяці тому

    please let me know how did you get the EV at £250?!

  • @alexxset
    @alexxset 3 роки тому

    Perfect lesson! Thank you a lot!!!!!

  • @MAAZWAHEED-j3e
    @MAAZWAHEED-j3e Рік тому

    Thank you!

  • @horrgakx
    @horrgakx 2 роки тому

    I don't get the EV though, I didn't pick up from the video what that is.

  • @Teodor-j1l
    @Teodor-j1l Рік тому

    The graph example is misleading and wrong. Curve should remain at 0 until payment is made to contractor. Currently the graph showd that we paid the contractor $ every day.

  • @eamon-GPT
    @eamon-GPT 2 роки тому

    How is the EV £250 calculated?

    • @7callisto
      @7callisto 7 місяців тому +1

      I think he said they only did 25% of the wall at that time. So the planned 1000 bricks at £250 plus labour £750 makes £1000. 25% complete of it is £250.