MRP Table and Calculations Updated)

Поділитися
Вставка
  • Опубліковано 3 гру 2024

КОМЕНТАРІ • 58

  • @okiedokie1875
    @okiedokie1875 7 років тому +3

    YOU ARE A LIFE SAVIOR!!
    I have my exam tomorrow and this is the example that I have in my book as well! I failed my quiz for this and now I can finally ace it in my exam. This helped me so much. God bless you!

  • @allannichols9864
    @allannichols9864 9 років тому +2

    Thank you Dr. Bharadwaj, I am a student at another PASSHE University taking an Operations Management course and this really helped me! I was presented with the same material, but for whatever reason I was missing the relevance of low level coding, and your video helped me put it all together. Many Thanks!

  • @ralphflores3324
    @ralphflores3324 4 роки тому +1

    Thanks! Explanation of how to order D and E was very helpful. Great job!

  • @kennywu1950
    @kennywu1950 3 роки тому

    Your video clear all my cloud of confusion understanding the MRP. Thank you so much

  • @عمرصران-غ7ق
    @عمرصران-غ7ق 11 місяців тому

    Thank you so much .. افضل من شرح MRP

  • @001shardul
    @001shardul 10 років тому +3

    Very knowledgeable and very descriptive for self learners!!!

  • @riceburger
    @riceburger 9 років тому +2

    THANK YOU THIS CHANGED MY LIFE I AM ETERNALLY GRATEFUL :,)

  • @akansharammaiya2605
    @akansharammaiya2605 6 років тому +1

    Great Video Sir. All concepts got cleared.

  • @antimisinfo4928
    @antimisinfo4928 9 років тому +4

    Thank you very much for this amazing explanation!

  • @floydmartyres9157
    @floydmartyres9157 2 роки тому

    Great stuff...cleared any confusion i had.

  • @omarramahi383
    @omarramahi383 5 років тому +1

    Amazing teacher.thank you so much!

  • @moayadibrahim9811
    @moayadibrahim9811 4 роки тому

    thank you so match, it's been a long time on this caption but that is really helpful

  • @oliviermaclean41
    @oliviermaclean41 4 роки тому

    Thank you for this video. Amazing and simple explanation!

  • @muradquliyev6448
    @muradquliyev6448 5 років тому +1

    Thanks for good explanation.

  • @jncm1945
    @jncm1945 10 років тому +1

    Excellent explanation, thanks for sharing.

  • @milankovacic9474
    @milankovacic9474 7 років тому

    Incredible explanation. Thank you very much.

  • @SuperSmilingHeart
    @SuperSmilingHeart 9 років тому +5

    Thank you so much! This is definitely going to help me for my final!

  • @iamaviplovebigbang
    @iamaviplovebigbang 5 років тому

    thanks a lot~ I won't be able to take my final without this

  • @maniprasad870
    @maniprasad870 8 років тому +1

    thank u vry much sir for ur neat and clear explanation!!! was very helpful

  • @goodboysady
    @goodboysady 6 років тому

    Paper on Monday cramming shit up on Saturday night.
    Long live utube

  • @stephensimmons8567
    @stephensimmons8567 8 років тому

    Mr. Bharadwaj do you have any video about Customs Issues & Procedures and International Transportation and Trade,also Essentials of Freight Forwarding, customer service and sales and Inventory control

  • @lampsizgod
    @lampsizgod 6 років тому

    Shouldn't the projected on-hand be zero for each of the materials A,B,C in the weeks 8,7,7? There is no Safety Stock consideration. If SS were considered, then the on-hand numbers are correct but the net requirements would change to 50,80 and 120.

  • @TheJaebeomPark
    @TheJaebeomPark Рік тому

    great video!

  • @rafandralazuardi9463
    @rafandralazuardi9463 9 років тому +2

    Thx you man !!!!! Really awesome

  • @김태균-x3k
    @김태균-x3k 10 років тому +1

    Thank you for your lecture :)

  • @MaududHassanUzzal
    @MaududHassanUzzal 8 років тому +1

    The first gross requirement 50. Will it be given or we have to somehow find it ourself?
    Thanks in advance

    • @prashanthbharadwaj9771
      @prashanthbharadwaj9771  8 років тому +1

      It comes either from the MPS of from the planned order releases of the parent item. In this problem, it was given.

    • @MaududHassanUzzal
      @MaududHassanUzzal 8 років тому

      Thanks

    • @mallutv3695
      @mallutv3695 4 роки тому

      @@prashanthbharadwaj9771
      Sir , here we've demand "50" came on 8th week only?
      Will it come on other week columns as well?

    • @prashanthbharadwaj9771
      @prashanthbharadwaj9771  4 роки тому +1

      @@mallutv3695 It certainly can. This is a simple example of one order (demand) in week 8. In reality, there can be demand in each of the weeks in the planning horizon.

    • @mallutv3695
      @mallutv3695 4 роки тому

      @@prashanthbharadwaj9771
      Thankyou for replying sir...
      One more doubt,
      How we do this problem, if "order quantity" is given in the question for each items?

  • @nipurchawla2541
    @nipurchawla2541 5 років тому

    What if quantity of D is 1 (meaning you need 1 D to male 2 B’s and need 1 D to make 2 F’s and 3 C’s.)
    How would you calculate D’s demand? Same way by multiplying parents and children? Please advise

  • @ahmedjaved2201
    @ahmedjaved2201 7 років тому

    Thank you Sir, Very Helpful.

  • @abhi-lu3hv
    @abhi-lu3hv 6 років тому

    Thanku so much sir ..it is very helpfull !!!

  • @SonuSingh-tx3uz
    @SonuSingh-tx3uz 5 років тому

    Can you please share the video for DRP like same as MPS and MRP.

  • @MidnightDestroyerMedia
    @MidnightDestroyerMedia 7 років тому

    This was so helpful and thorough! Thank you

  • @TheSniper001000
    @TheSniper001000 8 років тому

    what can i do if there's common parts and the PO release for the upper parts are in the same week, which GR value i must use !?

    • @prashanthbharadwaj9771
      @prashanthbharadwaj9771  8 років тому

      +Fares Ayyad Write to me in detail on pnb@iup.edu and I will be happy to respond.

    • @TheSniper001000
      @TheSniper001000 8 років тому

      +Prashanth Bharadwaj thank you for respond and i'll contact you.

  • @skoopysallu
    @skoopysallu 7 років тому +1

    THANKS SAIRRE!!!
    ALLAH BLESS YOU :D

  • @macrosweb8132
    @macrosweb8132 4 роки тому

    good job.

  • @merieml.2248
    @merieml.2248 9 років тому +1

    thank you !! very helpful explanation

  • @G1llmanBlacklg00n
    @G1llmanBlacklg00n 11 років тому +1

    This video does not really play back very well

  • @kv_karan
    @kv_karan 2 роки тому

    thanks

  • @breadpitt2475
    @breadpitt2475 4 роки тому

    Thanks

  • @becreative14
    @becreative14 10 років тому

    Thanks a lot sir.

  • @saadullahkhanwarsi5853
    @saadullahkhanwarsi5853 4 роки тому

    Thanks alot

  • @faisaladi4822
    @faisaladi4822 7 років тому

    thank you mister :))

  • @teezbar
    @teezbar 10 років тому

    Thank you!!

  • @Iwtvprintern
    @Iwtvprintern 7 років тому

    thank youuuuuuuuuuuu so muchhhhhhhhhhhhhhh

  • @bibobnoor1030
    @bibobnoor1030 6 років тому

    thanks a lot sir

  • @jameskrishnan
    @jameskrishnan 8 років тому

    Sir 16 D's for 100 A's? or 16 D's for 1 A?

    • @himand11
      @himand11 7 років тому

      16 D's for 1 A

  • @aakashswamy8707
    @aakashswamy8707 4 роки тому

    Plzz any one can explain about lead time please I am confusing

  • @sankalp7135
    @sankalp7135 7 років тому

    All class

  • @v4vannatta521
    @v4vannatta521 6 років тому

    Thank you!