At roughly 6.03 into the video, you discuss having an LA before and after the Transformer. Are these LAs part of the station or are they attached to the Transformer itself? Thanks
To isolate the parts of the parties in case of failure so that the workshops can perform maintenance and ensure the isolation and grounding of all parts damaged
Is great course you are conducting. One question, why sizes of bar uninuslated copper wires connected from power transformers to the grid ground of substation yard is large for example 4*185 sqmm2 while line to ground fault is small ?
Hi I am doing my final year project. Can you do a video to represent the SLD in software such as DIgSilent powerfactory 15.1, particularly focusing on substation. To perform load flow and contingency analysis.
So I would need for you to modify the Single Line Diagram of adding a Step Down Section from 33 KV to 11 KV , after the measurement section and then depart the three outgoing section from the 11 KV .
Though Rated voltage for 33kV Nominal System Voltage is mentioned as 36kV, while mentioning the ratio of Trafo, you probably need to mention 33/11kV and not 36/11kV.
@@GauravJ Of course, but good electrical system design strives to minimize too high switching overvoltages. IOW, if the arresters are actived during such operations something isn't quite right. For this reason VCBs are not installed in France in systems above 11 kV since 1990s
Do you have video on switchgear batteries, there use, why its required and when its not required?
145/36kV. Thank you.
should there be earthing switches on the lower transformer branches?
How can I get the schematic to practice on it?
Great video, please make more videos like this. Specifically protection SLD and control schematics.
Why is there no voltage transformer for metering and protection on the incoming side?
Hi, can you do complete video of how to do the trouble shooting of the circuit breakers and transformers in a substation.
Where is placed voltage transformer.?
145/36kv
Great lecture..
Can we use Delta/ Delta Transformer? Any advantages?
Very helpful ! Thanks
Sir,
The Earth Switch is Incoming Side,but it is not correct way.
Kindly make video on 22/420√3 KV
400 kV 1(1/2) breaker scheme switchyard
At roughly 6.03 into the video, you discuss having an LA before and after the Transformer. Are these LAs part of the station or are they attached to the Transformer itself? Thanks
It is a dedicated device and will be connected separately..
3 incommmer 2bus coupler ats system please explain sir..
Great lecture...pls explain dol sld too...
Is lighting arrester and Surge arrester(IEC/VDE/NEMA panel) same ?
Why do we have relay and cb first and later cb and relay before transformer???
To isolate the parts of the parties in case of failure so that the workshops can perform maintenance and ensure the isolation and grounding of all parts damaged
Nice video. Thank you 👍🙏
Sir , please upload video on what is the work of Electrical engineer or supervisor on site, how to start it as a fresher..??
Thank you.
Is great course you are conducting. One question, why sizes of bar uninuslated copper wires connected from power transformers to the grid ground of substation yard is large for example 4*185 sqmm2 while line to ground fault is small ?
Hi I am doing my final year project. Can you do a video to represent the SLD in software such as DIgSilent powerfactory 15.1, particularly focusing on substation. To perform load flow and contingency analysis.
Sir please Explain 33kv Substation Lay Structure With Cad Thankyou Sir
VERY HELPFUL.
So I would need for you to modify the Single Line Diagram of adding a Step Down Section from 33 KV to 11 KV , after the measurement section and then depart the three outgoing section from the 11 KV .
Though Rated voltage for 33kV Nominal System Voltage is mentioned as 36kV, while mentioning the ratio of Trafo, you probably need to mention 33/11kV and not 36/11kV.
Can you send me about grounding lectures?
Thank you sir
Thank you for your help ☺️☺️☺️
145/36 Kv
145/36 Kv
Thanks for the feedback 😊
@@GauravJ Where is PT
Please do videos on power systems 2....... Please
Lightning arrestors should primarily protect against lightning overvoltages, no?
Yes. It also protects from the switching overvoltages.
@@GauravJ Of course, but good electrical system design strives to minimize too high switching overvoltages. IOW, if the arresters are actived during such operations something isn't quite right. For this reason VCBs are not installed in France in systems above 11 kV since 1990s
where is the auxiliary transformer????
Where is voltage tf
Helpful
Link
145 kV/ 33 kV sld scheme
Please do SLD 145/36 KV
Hi. The video is available
Single line diagram (SLD) of 132/33kV Substation | Explained | TheElectricalGuy
ua-cam.com/video/AM-ROAd1wxU/v-deo.html
145/36 kv
145/36 kV
SLD 145/36kv
Yes of course 145/36kv
145/36
please 145/66
👌🏻
❤
Much too much to absorb for a new learner at one time.
145/36 Kv
Single line diagram (SLD) of 132/33kV Substation | Explained | TheElectricalGuy
ua-cam.com/video/AM-ROAd1wxU/v-deo.html
220/30
145/36 kv.
Thank you sir
Thank you.
145/36kv
145/36kV
145/136 kv
145/36
145/36kV
145/36 kv
145/36kv
145/36
145/36
Hi. The video is available
ua-cam.com/video/AM-ROAd1wxU/v-deo.html