Yes, u are right..that is a calculation error. i wrote 0.96 instead of 8.96 | Quantity of PCC = (44.8*.2*1) =8.96 cubic meters. thank u for the comment.
sir in 3.17 minute you said total quantity pcc work in foundation is 0.96 cubic meter , but actually I think it is 8.96 cubic meter. kindly check it out sir 🤝
pcc value 8.96 plz check
I have the same doubt
Yes, u are right..that is a calculation error. i wrote 0.96 instead of 8.96 |
Quantity of PCC = (44.8*.2*1) =8.96 cubic meters.
thank u for the comment.
@@camcivilarchmentor384 thanx sir its been great to see u r reply
8.96 alle pcc value
sir in 3.17 minute you said total quantity pcc work in foundation is 0.96 cubic meter , but actually I think it is 8.96 cubic meter. kindly check it out sir 🤝
Haa 8.96 correct
Thank u sir👍sharing to friends
SUPER EXPLANATION SIR
Thank you❤❤
Pwoli
👍👍Pwoli
Thnks sir
Thanks sir
So nice of you
Thanks
Thanks a lot brother❤️❤️❤️❤️❤️
u r welcome..
2:58 height kayinja videoyil 0.8 aanallo…ippam entha 0.2 aayath
Pls do steel quantity calculation of lintel sunsade slab
Plinth projection illengilo ❓
Sir earthwork excavation for foundation kazchinitallee , quantity of PCC for foundation cheyandathu?
As per the question...
Order is not important.. Just calculate what ever asked for.....
😍
Plinth projection vannilla
Ethil pcc quantity amount mistakes ennddd ..
Thankyou sir
u r welcome