Conventional Shuttering Procedure l 8 Days Slab Cycle I Ply Shuttering

Поділитися
Вставка
  • Опубліковано 16 лип 2021
  • Slab cycle for high Rise Building with conventional shuttering
    In this video, we talk about 8 days slab cycle with conventional ply shuttering, will discuss the procedure with the activities to follow on-site each day to achieve 8 days cycle
    This video covers all these topics
    Day 1
    - Starter work with centre line drawing
    - Complete vertical column, shear wall reinforcement work
    Day 2
    - Column Shuttering
    Day 3
    - Column Concrete work 100% complete
    Day 4
    - Slab Shuttering start (Beam bottom, Beam side, Slab shuttering)
    Day 5
    - Complete Beam and slab reinforcement work with covering
    Day 6
    - Complete all Electrical Conduiting work and MEP sleeves and cutouts if needed
    Day 6
    - Complete Gridline checking and supporting work of slab
    Day 7
    - Complete checking work of RCC, architect, quality, and MEP work as per approved drawing and with respecting departments
    Day 8
    - Finally, do Concrete Casting work of slab
    and many more...
    ___________________________________________________
    Share, Support & Subscribe👇👇👇
    Subscribe: ua-cam.com/users/DNDConstruc...
    UA-cam: / dndconstruction
    Blogger: dndconstruction.blogspot.com/...
    Facebook: / dndconstructioncompany
    LinkedIn: / dnd-construction-85870...
    Instagram: dnd_constru...
    Telegram: t.me/dndconstruction
    Twitter: ConstructionDnd?s=09
    _____________________________________________________
    #8daysslabcycle #slabcycletime #slabcycleforhighrisebuilding
    8 days slab cycle work activities to be followed on site for high rise building construction
    slab cycle in construction
    ____________________________________________________
    Disclaimer for my UA-cam channel
    The Content in this video is strictly for educational and informational purposes and is not intended to be advice or recommendation of any kind whatsoever.
    ____________________________________________________
    About Channel:
    DND Construction: This channel has Technical & Practical Civil Engineering & Construction videos based on field experience for all Civil Engineers & Construction professionals.
    Email Id for Inquiry: dndconstructioncompany@gmail.com
    Channel Host: Narendra Patle (BE, ME in CEM with 7+ years of Industry Experience)
    #dndconstruction #civilengineernarendrapatle
    ✌DND Construction by Narendra Patle 👷‍♂️

КОМЕНТАРІ • 6

  • @vinodrathod6180
    @vinodrathod6180 3 роки тому +1

    Very Good explanation, can you share area of slab and manpower carpenters, carpenter helpers , steel fitters , steel fitters helpers , skilled & unskilled workers deployed for slab in this video.
    Thank you.

  • @vandeutkalajanani2273
    @vandeutkalajanani2273 10 місяців тому

    And curing

  • @nachiketmirkar4653
    @nachiketmirkar4653 2 роки тому

    Very well explained

  • @AkashPatil-mn6jm
    @AkashPatil-mn6jm 2 роки тому

    I like it 👌👌👌👌❣️❣️❣️❣️

  • @user-gj9pg2wi9z
    @user-gj9pg2wi9z Рік тому

    There are some falws in the explaination. I have seen 12days slab cycle till now. was curious to know about 8 days but, there should be detailed explaination and also, the time taken to complete aactivities like formwork fixing etc. seems hypothetical whereas practically much more time is rquired. Especially Day 4, Day 5 & Day 6 seems problamatic. Although, full marks for efforts taken to make this video.

  • @vandeutkalajanani2273
    @vandeutkalajanani2273 10 місяців тому

    Minimum 12 days required