31 | Revised Schedule: Delay Events, Extensions, and Practical Analysis

Поділитися
Вставка
  • Опубліковано 3 гру 2024

КОМЕНТАРІ • 5

  • @AsaadAlamir
    @AsaadAlamir Місяць тому +1

    Thx Eng Hani but could you elaborate why 18 days is not compensable (although it is excusable) and this delay (18 days) is caused by client and that's why contractor has the right to claim for cost also since project finish date will shift 18 days further

  • @syedobaid3631
    @syedobaid3631 Місяць тому

    You didnt explain why there was an 18 day impact on a 14 say event

  • @hamzarehman4948
    @hamzarehman4948 26 днів тому

    Sir can u please a practical video for me where project finished date change from March to February. 1 month before the project end date

    • @PlanningengineerNet
      @PlanningengineerNet  22 дні тому +1

      Hello Engineer, check your critical path and adjust it to fit your planned finish date.

    • @hamzarehman4948
      @hamzarehman4948 22 дні тому

      @PlanningengineerNet okay sir