Crashing in PERT and CPM || Crashing of Project Part 1 in hindi with solution by JOLLY Coaching

Поділитися
Вставка
  • Опубліковано 18 вер 2024
  • This video will help you to solve your Crashing Problems in operation research, this video include a solved question of Crashing which will tell you the steps involved while doing crashing of a project.
    Link for best OR Book : amzn.to/2A34QCL
    Link for Pert Video : • PERT (Project Evaluati...
    Link for Cpm video : • Critical Path Method(C...
    Crashing refers to reducing the time duration of any project or to complete the whole project before the normal time of the project.
    So basically it is a technique which is useful for the business organisation to reduce the time of the project.
    I hope this video will help you to understand the basis concept of crashing the project using pert and cpm in hindi.
    Thanks
    JOLLY Coaching
    Crashing in pert and cpm
    Crashing in pert and cpm in hindi
    crashing of project
    crashing of project network
    project network
    network analysis
    crashing in network analysis
    crashing in hindi
    crashing in hindi
    crashing of project in hindi
    crashing of project analysis in hindi
    crash in hindi
    crash
    crashing questions
    in hindi
    crashing,crash,crashing in pert and cpm,crash in pert,crash in cpm,crashing in pert,crashing in cpm,crashing in pert and cpm in hindi,cpm,pert,pert and cpm in hindi,crashing in hindi,crashing of network in pert and cpm,crashing of network,crashing of activities in cpm,crashing of project,crashing probiem,crashing problem in pert and cpm,crashing solved question,project crashing,crashing of project in hindi,crashing of projects in project management,or,btech,ca

КОМЕНТАРІ • 36

  • @virajkharva8561
    @virajkharva8561 6 років тому +3

    Very nice teaching skills of yours.. Through grasped & understanding.. Your explanation is through & useful for whole topic.. There will not be any problem for me in solving other examples cause of your excellent and easy to understand explanation....

  • @ibrahimsabthasildar7507
    @ibrahimsabthasildar7507 4 роки тому +1

    Thank you very much 😊 sir 👍😊 🙏 ji aap me Mera dought clear kardiye hooooooooooooo,

  • @exotickhanaarif4333
    @exotickhanaarif4333 6 років тому +4

    I am cma student i have to say ur videos are helping me in understanding operation management keep it up make many more videos like that

    • @shriyarath6743
      @shriyarath6743 6 місяців тому

      Aap k cma complete hogaya kya bhaiya?

  • @firstanimeexplainer2753
    @firstanimeexplainer2753 5 років тому +1

    thank you so much sir...very helpful videos

  • @KokabManzoor
    @KokabManzoor 2 роки тому

    very well explained..

  • @umaisafarooq5907
    @umaisafarooq5907 2 роки тому

    U e nice nice teacher plz make vedio on functions

  • @ThePranalipote48
    @ThePranalipote48 6 років тому +4

    can you explain me how to plot graph with indirect direct total cost and time

  • @ShivamKumar-yc1zs
    @ShivamKumar-yc1zs 6 років тому

    Sir aap bahut acha padhte hai agar aap nahi hote UA-cam channel Mai Hume kabhi Bhi yeh subject nahi padh pate. Sir aap sabhi video turant bhej Diya Kare.. Thanks sir

  • @rahullokwani173
    @rahullokwani173 6 років тому

    it helped me a lot sir thank u very much.

  • @architasharma8017
    @architasharma8017 2 роки тому

    thnku sir 🥰🥰🥰❤🙏😇

    • @jollycoaching4214
      @jollycoaching4214  2 роки тому +1

      Please Share
      ua-cam.com/play/PLMGRv4j_3EZZJJsTERwAQmrToTHQS22Py.html

  • @prateekverma73
    @prateekverma73 6 років тому

    Bhai very good yrrr mza aa gya

  • @bhagyeshpawar8299
    @bhagyeshpawar8299 4 роки тому

    Thankyou🙌 very helpful

  • @heena1585
    @heena1585 4 роки тому

    Good job sir

  • @yashupintu1
    @yashupintu1 6 років тому +1

    sir , 27:00 min, par b common le liya par it is common only between 2 paths , and not all three paths. so should common activity be common in all the paths selected or only any 2 paths?

  • @anishar3811
    @anishar3811 6 років тому +1

    Sir, pls solve the 2nd and 3rd type of crashing problem

  • @madhavadhikari6943
    @madhavadhikari6943 5 років тому

    Please jolly coaching i need vdo of sensitivity analysis of lpp

  • @KajalGupta-gk3vq
    @KajalGupta-gk3vq Рік тому

    ❤️❤️❤️

  • @yemaneamare8027
    @yemaneamare8027 5 років тому

    nice expression

  • @DesignReady.
    @DesignReady. 5 років тому

    You can't loose the Critical path after it get created ... ..?

  • @faizraina7946
    @faizraina7946 3 роки тому +1

    Table mai values toh dalo . Vo kaise kare

  • @karannagvekar2929
    @karannagvekar2929 5 років тому +1

    24:00 me uncommon activity ke cost ko kyu add kiya?

  • @devendrapatel1601
    @devendrapatel1601 6 років тому

    Sir plzzzz IRR ka video bnao

  • @devendrapatel1601
    @devendrapatel1601 6 років тому

    Sir part 2 bnao jldi

  • @mdaamirhussain9118
    @mdaamirhussain9118 5 років тому

    Sir, last me hamne 'C' ko 'F' ko dono ko 5-5 days crash kiya hai to total Hame last me 10 days crash kiya hai sir, fir Aap ne 5 days ko hi kuy liya

  • @abiddar5803
    @abiddar5803 3 роки тому

    Indirect Cost toh Kam hojati hai na. Wo concept to ismain aapne dikhaya hi nai hai

  • @sushmitarai8173
    @sushmitarai8173 5 років тому +1

    In my question there is just simple pert diagram and is asked yo crush
    But here there are given crashing time
    What should I do😑😑😭😭😭

  • @mayankjain7604
    @mayankjain7604 5 років тому

    PERT CPM ke 4 video hi h ya koi or h

  • @hajlklsijko
    @hajlklsijko 3 роки тому

    30:30 105 not 115

  • @GouravTECH
    @GouravTECH 5 років тому +1

    Very confusing topic

  • @Orthodox19.
    @Orthodox19. 2 роки тому

    why not speak in English ?

    • @jollycoaching4214
      @jollycoaching4214  2 роки тому

      Lecture is in Hindi (Hindi Is Our National Language)
      Please share
      ua-cam.com/play/PLMGRv4j_3EZZJJsTERwAQmrToTHQS22Py.html