- This video will help you to solve your Crashing Problems in operation research, this video include a solved question of Crashing which will tell you the steps involved while doing crashing of a project.
Link for best OR Book : amzn.to/2A34QCL
Link for Pert Video : • PERT (Project Evaluati...
Link for Cpm video : • Critical Path Method(C...
Crashing refers to reducing the time duration of any project or to complete the whole project before the normal time of the project.
So basically it is a technique which is useful for the business organisation to reduce the time of the project.
I hope this video will help you to understand the basis concept of crashing the project using pert and cpm in hindi.
Thanks
JOLLY Coaching
Crashing in pert and cpm
Crashing in pert and cpm in hindi
crashing of project
crashing of project network
project network
network analysis
crashing in network analysis
crashing in hindi
crashing in hindi
crashing of project in hindi
crashing of project analysis in hindi
crash in hindi
crash
crashing questions
in hindi
crashing,crash,crashing in pert and cpm,crash in pert,crash in cpm,crashing in pert,crashing in cpm,crashing in pert and cpm in hindi,cpm,pert,pert and cpm in hindi,crashing in hindi,crashing of network in pert and cpm,crashing of network,crashing of activities in cpm,crashing of project,crashing probiem,crashing problem in pert and cpm,crashing solved question,project crashing,crashing of project in hindi,crashing of projects in project management,or,btech,ca
Very nice teaching skills of yours.. Through grasped & understanding.. Your explanation is through & useful for whole topic.. There will not be any problem for me in solving other examples cause of your excellent and easy to understand explanation....
Thank you very much 😊 sir 👍😊 🙏 ji aap me Mera dought clear kardiye hooooooooooooo,
I am cma student i have to say ur videos are helping me in understanding operation management keep it up make many more videos like that
Aap k cma complete hogaya kya bhaiya?
thank you so much sir...very helpful videos
very well explained..
U e nice nice teacher plz make vedio on functions
Thanks for watching
Please share
can you explain me how to plot graph with indirect direct total cost and time
Sir aap bahut acha padhte hai agar aap nahi hote UA-cam channel Mai Hume kabhi Bhi yeh subject nahi padh pate. Sir aap sabhi video turant bhej Diya Kare.. Thanks sir
it helped me a lot sir thank u very much.
thnku sir 🥰🥰🥰❤🙏😇
Please Share
ua-cam.com/play/PLMGRv4j_3EZZJJsTERwAQmrToTHQS22Py.html
Bhai very good yrrr mza aa gya
Thankyou🙌 very helpful
Good job sir
sir , 27:00 min, par b common le liya par it is common only between 2 paths , and not all three paths. so should common activity be common in all the paths selected or only any 2 paths?
Sir, pls solve the 2nd and 3rd type of crashing problem
+Anisha R
Ok
Please jolly coaching i need vdo of sensitivity analysis of lpp
❤️❤️❤️
nice expression
You can't loose the Critical path after it get created ... ..?
Table mai values toh dalo . Vo kaise kare
24:00 me uncommon activity ke cost ko kyu add kiya?
Sir plzzzz IRR ka video bnao
Sir part 2 bnao jldi
+devendra patel
Ok
Sir, last me hamne 'C' ko 'F' ko dono ko 5-5 days crash kiya hai to total Hame last me 10 days crash kiya hai sir, fir Aap ne 5 days ko hi kuy liya
Indirect Cost toh Kam hojati hai na. Wo concept to ismain aapne dikhaya hi nai hai
In my question there is just simple pert diagram and is asked yo crush
But here there are given crashing time
What should I do😑😑😭😭😭
PERT CPM ke 4 video hi h ya koi or h
30:30 105 not 115
Very confusing topic
why not speak in English ?
Lecture is in Hindi (Hindi Is Our National Language)
Please share
ua-cam.com/play/PLMGRv4j_3EZZJJsTERwAQmrToTHQS22Py.html