  • This video will show you how to automatically load the work coordinates using the G10 command.

КОМЕНТАРІ • 10

  • @bikefarmtaiwan1800
    @bikefarmtaiwan1800 3 роки тому +1

    Very clear and helpful! Subbed!

  • @jonathanmota8887
    @jonathanmota8887 4 роки тому

    how does this work out when working with stock say castings which can be sometimes over size up to an inch in any direction? This seems to be maybe a crash maybe?

  • @sellenger
    @sellenger 8 років тому

    Love the these vids !!

  • @RICREYNOLDSMUSIC
    @RICREYNOLDSMUSIC 4 роки тому

    I started a new job on some Horizontals and they are using G10 on all the machines. The problem is that if you have to rerun a sequence, you have to manualy/MDI the G10 start up program so you don`t scrap a part. These are military grade parts and I think there is a way to have the program reload the G10 numbers so it doesn`t scrap the part. Is there a way to safeguard a program to load the G10 lines before every sequence? They told me it is not possible.

  • @danielmckeever8241
    @danielmckeever8241 3 роки тому

    I use G10 all the time to load tool offsets.
    For Example, my driven tools for a particular job:
    G10 P10002 X -300.000 R 10.000 Q0.
    G10 P10003 X -300.000 R 5.000 Q0.
    G10 P10004 X -300.000 R 3.000 Q0.
    G10 P10005 Z -40.000 R 0.750 Q0.
    G10 P10009 Z -40.000 R 0.000 Q0.
    G10 P10010 Z -40.000 R 1.250 Q0.
    This prevents the machine setter forgetting to manually input the non-probed geometry values. (I've done it)
    My CAM package always outputs work offsets like this:
    G10 L2 P1 etc etc
    G10 L2 P2 etc etc
    G11
    The manual says G11 is Programmable Data Input Cancel. My question is why should I use G11?
    If I don't use G11 the data still goes where I want it, and no other data is stored or overwritten until I manually change something or run another G10 line. In which case what's the point of G11?
    Why do I need to tell the NC that I'm finished inputting data? The data input is finished so I just drive on.
    Just curious

  • @steelcapthunder
    @steelcapthunder 5 років тому +1

    Can this method be used on a lathe for Z and C work offsets?

  • @muhndkalil9234
    @muhndkalil9234 7 років тому

    Hi, I have qeustion . when I start the machine the will go to the limet switch and set it home the
    and when I put work pics in the table of the machine I shoud to make another home position to the work pics in the edge of the work pics the qeustion is when I have
    G10L2 P1 X5Y3Z4 this cordinate value will add to the first home position of the machine or to the home position of the work pics???

  • @Lacika19810507
    @Lacika19810507 7 років тому

    Thank you

  • @EkAdivasiraj
    @EkAdivasiraj 5 років тому

    Please make videos on L20