    9.According to official language rule 1976 (as amended 1987), communication from a central government office to state or union territory or to any office in Region "A" (not being a central government office) shall be in
    Ans: Option A (Hindi)
    13. Extra clearance required for two adjacent curve will be
    Ans: Option: C (ET+OT+ 2SWAY)
    22. Answer of Q no 22 is d
    Para 6.2 (iiii) of Specifications of Railway Formation says that N value (determined from Standard Penetraion Test- SPT) Less than 5
    24. The period of consolidation for BG concrete sleeper track
    Ans: Option A
    42. If a Railway servant is transferred to a station that is within 20 km from the old station & does not involve change in residence, CTG admissible will be.
    Ans: Options C (NIL)
    46. In Breathing length which of the following is true
    Ans: option C ( Thermal forces gradually increased from from SEJ to Central portion). This can be seen in force diagram.
    74. "The maximum value of cant excess for a B.G.____mm curve on I.R. is
    Ans: Option C (75 mm)

  • @pintukumar-tr9wp
    @pintukumar-tr9wp 5 місяців тому

    sir please explain dynemic gauge

  • @riyuthakre8733
    @riyuthakre8733 2 місяці тому

    Sir ye que. Banaya kisne hai ye to je work ka lag rha hai ji

  • @manojojha5657
    @manojojha5657 6 місяців тому

    Answer of Q no 22 is d
    Para 6.2 (iiii) of Specifications of Railway Formation says that N value (determined from Standard Penetraion Test- SPT) Less than 5

  • @My.CartoonTV
    @My.CartoonTV 6 місяців тому

    किसके कितने नंबर बन रहे हैं ये तो बताओ

  • @mandeepphogat5986
    @mandeepphogat5986 6 місяців тому

    Sir ,Question se to Je works ka paper lg rha h , pway me b essa question puch skte h kya

    • @sutikshnkumar515
      @sutikshnkumar515 16 днів тому

      One of the togphest paper for ldce je in Indian railway

  • @m.r.barana9334
    @m.r.barana9334 6 місяців тому

    Question 42 Correct answer C as per RBE 103/2017

  • @tamannabegum2251
    @tamannabegum2251 6 місяців тому

    89 question ka English version dekhen at every 3 metre hoga

  • @DharmendraKumar-nr9oe
    @DharmendraKumar-nr9oe Місяць тому

    Sir ji aapka voice break hota hai please improve

  • @jitendrakumar-lw3hj
    @jitendrakumar-lw3hj 6 місяців тому

    Q.46 right answer D
    more details see IRPWM 335

    • @Kanurasiyacompany-r9x
      @Kanurasiyacompany-r9x 6 місяців тому +1

      You are wrong. Option A is right
      क्योंकि breathing length में temp. Change के कारण movement होता है परन्तु central portion में कोई expansion या contraction नहीं होता है जो कि central portion में thermal forces का निर्माण करता है

    • @jitendrakumar-lw3hj
      @jitendrakumar-lw3hj 6 місяців тому

      @@Kanurasiyacompany-r9x हो सकता है मैं रॉन्ग हु लेकिन IRPWM तो रॉन्ग नही होगा
      Please see IRPWM para 335

    • @JAREDA123engineer
      @JAREDA123engineer 6 місяців тому

      Yes

    • @trackengineer
      @trackengineer  6 місяців тому

      Q46. Option A may be incorrect but as per force diagram answer should be C

    • @jitendrakumar-lw3hj
      @jitendrakumar-lw3hj 6 місяців тому +1

      @@trackengineer सही उत्तर D है कृपया IRPWM को सही से देखे

  • @gajendrapalsingh7643
    @gajendrapalsingh7643 4 місяці тому

    94 में 1:81/2 में TWS को काट रहे हैं और 95 में sleeper की संख्या बता रहे हैं क्लियर it

  • @tamannabegum2251
    @tamannabegum2251 6 місяців тому

    Sir aap ke hisab se kitna cut off ja sakta hai

  • @m.r.barana9334
    @m.r.barana9334 6 місяців тому

    Kindly see question no. 74 again

    • @trackengineer
      @trackengineer  6 місяців тому

      Oh, It's big mistake. It should be 75 mm

    • @trackengineer
      @trackengineer  6 місяців тому

      Oh Really sorry, it is mistaken . it should be 75 mm

  • @jitendrakumar-lw3hj
    @jitendrakumar-lw3hj 6 місяців тому

    Q 42 राइट उत्तर C
    Ctg तभी मिलेगा जब आवास चेंज हुआ हो

  • @Kanurasiyacompany-r9x
    @Kanurasiyacompany-r9x 6 місяців тому +1

    Q 24 का सर option A होगा
    50,000 gross tonnes of traffic or a period of two days whichever is later.
    (यहां पर later है ना कि earlier)

  • @manojojha5657
    @manojojha5657 6 місяців тому

    Very nice sir
    Another teacher of u tuber said that answer of Q no 13 is c but according to u answer is a. Sir Plz confirm which is ryt.

    • @trackengineer
      @trackengineer  6 місяців тому

      Q. No 13 right answer is option c .I have updated in description box of this question

  • @tamannabegum2251
    @tamannabegum2251 6 місяців тому

    Sir cutt off kya hoga

  • @ranjeetpaswan3617
    @ranjeetpaswan3617 6 місяців тому

    Very good sir 👍

  • @jokesislife6254
    @jokesislife6254 4 місяці тому

    16 ka c hai

  • @jitendrakumar-lw3hj
    @jitendrakumar-lw3hj 6 місяців тому

    Q . 9 सही उत्तर A हिंदी होगा

  • @manishkumarmeena4040
    @manishkumarmeena4040 6 місяців тому

    109 question answer c hoga 1 in 400

  • @nehastudies.
    @nehastudies. 6 місяців тому

    Sir आंसर को रिपीट कर दिया करे

  • @jitendrakumar-lw3hj
    @jitendrakumar-lw3hj 6 місяців тому

    Q.109 right answer C as per SOD

    • @trackengineer
      @trackengineer  6 місяців тому

      My dear, whenever gradient to keep steeper than 1:1200 to 1 in 400, approval of GM is required for all new works. Here question has asked, "without any special approval"

    • @jitendrakumar-lw3hj
      @jitendrakumar-lw3hj 6 місяців тому

      @@trackengineer gm approval not required please see sod

    • @trackengineer
      @trackengineer  6 місяців тому +2

      However, for new yards in new line projects adoption of yard gradient steeper than 1:1200 will require approval of General Manager before finalization of ESP.

  • @jitendrakumar-lw3hj
    @jitendrakumar-lw3hj 6 місяців тому

    Q.13 सही उत्तर C