Soil Mechanics : California Bearing Ratio (CBR) Test - Hinawan T. Santoso, ST, MT
Вставка
- Опубліковано 19 вер 2024
- Hello guys ...
This time there is an Online Lecture at the Polytechnic PU supported by new media. What is that? Yups ... Tutorial video via youtube channel. This video tutorial was made as one of the supporting media for Distance Learning for the Soil Mechanics course in the Road & Bridge Construction Study Program, Public Works Polytechnic Campus, Semarang.
This video material is related to Soil Mechanics, with a focus on the CBR (California Bearing Ratio) Test. Outline of this video tutorial, i.e :
(a) Introduction and Theory of CBR,
(b) Laboratory CBR Test,
(c) Field CBR Test.
So ... don't forget to watch it until it's finished, so that you are smarter.
Hopefully this video tutorial is useful for you guys.
Click SUBSCRIBE and LIKE if you like.
Don't forget to COMMENT and SHARE via your social media.
Stay smart, stay safe & stay health.
See you on next video ...
Regards,
masdosen
Note:
The material was adapted from various sources, with modifications needed from masdosen.
Bagi rekan2 yang membutuhkan bahan paparan dari video edukatif di atas.
Silahkan email ke : hteguhsantoso@gmail.com
Saya sudah email pak, mohon perkenannya, trims
Siap. Sdh di reply. Semoga bermanfaat
@@masdosen terima kasih banyak, tp klo mslah materi belajar.. dikasih satu biasanya sy minta tambah yg lain juga.. 😊😊😁
@@uuksyaefudin8078 Hehe
khadry_ft@yahoo.com
Masya'Allah.. terima kasih ilmunya pak
Sama-sama, semoga bermanfaat
MasyaAllah barakAllah fikum bpk ats penjelasan ilmuny y sangat detail
Semoga barokah buat amalan bpk dan bermanfaat bagi kami yg menyimak terima kasih bpk🙏
Ammiinnn... 🙏🏻🙏🏻
Sudah saya subscribe mas... !! tombol loncengnya sudah saya tekan... tinggal nunggu update videonya....
Terimakasih support-nya mas
@@masdosen mau ikut kuliah via zoom nya gak mas dos...?
@@dewadurja kuliah online via google classroom. Zoom agak banyak menyita kuota, kasian rekan2 mahasiswa
Terimakasih banyak buat videonya Pak... semoga jadi sedekah jariah dan amalan di Mata Allah SWT...🙏🙏🙏
Amiin... Mudah2an bermanfaat
Terima kasih banyak video nya bapak😀😀. Sangat membantu
Siap. Sama2. Semoga bermanfaat
Makasih om.. sangat berguna
Siap. Semoga bermanfaat
Salam, sehat selalu... saya menyimak dan terima kasih atas ilmunya amat bermanfaat. ijin menggunakan ilmunya.
Silahkan. Terimakasih, semoga bermanfaat.. 🙏🏻
Terimakasih banyak masdosen atas ilmunya🙏
sama-sama, semoga bermanfaat
Terima Kasih atas videoanya, sangat bermanfaat pak...
sama2. semoga bermanfaat
Trims mas🙏
Penjelasan dan uraian nya sangat bermanfaat👍
Sama2, semoga bermanfaat
semangat terus buat materinya pak, saya sangat terbantu
Alhamdulillah...semoga terbantu dan bermanfaat
Pak Masdoen, bahas juga dong penggunaan alat Bengkelman beam (BB) dan cara pengolahan datanya
Terimakasih masukannya, kami tampung. Mudah2an ada kesempatan mendatang.
izin bertanya, untuk satu titik pengujian CBR itu mewakili berapa luasan tanah ya pak? terimakasih
bagus mas hinawan👍
Thanks om viko
mas mohon pencerahan, nilai yg benar a a maka pengujian diulang
a < b = b > a kenapa harus diulang ya?
Hal tsb dipersyaratkan dalam SNI 1738-2011-Metode uji cbr lapangan dan ASTM D4429-09a-Standard Test Method for CBR (California Bearing Ratio) of Soils in Place. Untuk alasan kenapa harus diulang, saya kurang paham. Dmk. Tks
mohon maaf sebelumnya pak saya mau nanya, untuk penentuan titik lokasi uji CBR lapangannya radius jarak per berapa meter pak? untuk nilai penetrasi yang dipakai sebagai data modulus subgrade apakah penetrasi 0,1" atau 0,2" pak?
Terimakasih masdosen penjelasannya. saya mau tanya gimana ya kalau kita merencanakan tebal minimum subgradenya?
Desain subgrade, subbase dan base bs merujuk ke Manual Desain Perkerasan Jalan 2017 (MDP 2017)
mw tanyak pak. emang nya alat DCP itu gak bisa nentukan CBM ya pak kok gadak di jelasin di sini
DCP juga bisa untuk CBR subgrade, subbase, atau basecourse secara cepat dan praktis. Tks
Klo sudah diperoleh nilai CBR, tahapan atau rumusan apa yg digunakan untuk disain perkerasannya
Bisa mengacu ke MDP (manual desain perkerasan) 2017. Silahkan bs didonlod disini www.google.com/url?sa=t&source=web&rct=j&url=binamarga.pu.go.id/v3/assets/files/NSPK/pembangunan_jalan/2017_SE%2520DIRJEN%2520MANUAL%2520DESAIN%2520PERKERASAN%2520JALAN%2520(REVISI%2520%25202017)%2520(STEMPEL)%2520FINAL.pdf&ved=2ahUKEwiDh4zcjO_sAhW9H7cAHZqHAagQFjAAegQIARAB&usg=AOvVaw39EMAjU-BjcLaDPx2f8F0C
Langkah2 perhtiungan cbr lapangan ad gak pak materinya? Tks
Mohon maaf blm ada. Tks masukannya.
mohon pencerahan..tumbukan 56 x 5 lapis atau 65 x 5 lapis..untuk CBR labnya..?
Menurut ASTM D 1883-07 "Typically, if the CBR for soil at 95 % of maximum dry unit weight is desired, specimens compacted using 56, 25, and 10 blows per layer is satisfactory.
Penetration shall be performed on each of these specimens". Dmk. Tks.
penggunaan tumbukan 56 x 5 lpis klo kita merujuk ke standar SNI Itu termasuk kategori pemadatan modified dengan ukuran mallx 6 inchi dan persyaratn smpel materialx yg dipakai yaitu lolos saringan 3/4" dan utk penggunaan tumbukan 65 x 5 nnti di pakai utk pembuatan smpel CBR yg variasi 65, 35,10 tmbukan klo gak ada perubahan dri speksifikasi bina marga yg terbaru gan...krng lebih bgtu gan
ijin Pak bertanya, apakah bisa nilai CBR laboratorium dipakai untuk CBR desain Tebal perkerasan jalan atau harus menggunakan CBR lapangan ?
Bisa saja, asal nantinya tanah dasar di lapangan memang ditreatment (direplace/dipadatkan, dsb) sedemikian rupa sehingga didapatkan nilai CBR-nya sama dgn CBR desain. Namun, bila tanah dasar eksisting tidak mendapatkan treatment ttt, maka ada baiknya digunakan nilai CBR lapangan untuk proses desain. Dmk. Tks.
Politeknik pekerjaan umum semarang ?, sma dgn politek negri yg tmbalang bukan ?
Beda. Politeknik PU baru terbentuk 1 tahun lalu, dibawah Kementerian PUPR
@@masdosen owwh kirain.. maaf baru tau...
@@masdosen Terimakasih share Ilmunya, SMOGA SEHAT DAN SUKSES SE;LALU YA
mohon maap pak.. jika penetrasi 0,2 lbh besar dari 0,1.. utk hasil cbr mana yg d ambil buat laporan?.
minimal 3 x pengujian tpi klo dri ketiga pengujian itu msih didapat nilai 0,2 lebih bsar dari 0,1 inchi maka yg dipake yg 0,2 inchi
Assalamu'alaikum pak mau tanya untuk perencanaan jalan raya jarak atar CBR Lapangan itu per berapa meter ya pak minimumnya dan maksimumnya berapa meter ya pak? Dan jarak CBR Lab itu juga per berapa meter ya pak?
Dalam SNI 1738:2011 tentang Cara Uji CBR Lapangan hanya diatur jarak minimum antar pengujian, yaitu untuk tanah Plastis minimum 17.78 cm dan tanah granuler minimum sebesar 38.10 cm. Untuk jumlah dapat disesuaikan kebutuhan menurut Spesifikasi yang dipersyaratkan untuk masing2 pekerjaan. Tks
Untuk 1 titik pengetesan mewakili berapa m2 pak ?
Dalam SNI 1738:2011 tentang Cara Uji CBR Lapangan hanya diatur jarak minimum antar pengujian, yaitu untuk tanah Plastis minimum 17.78 cm dan tanah granuler minimum sebesar 38.10 cm. Untuk jumlah dapat disesuaikan kebutuhan menurut Spesifikasi yang dipersyaratkan untuk masing2 pekerjaan. Tks
Mohon maaf politeknik PU membuka kelas weekend apa tidak ya pak🙏
Perkuliahan di Politeknik PU reguler pada hari dan jam kerja. Tks
Pengen daftar😀 tapi terlanjur di Unnes SMT 5 pak
@@erliadevi10 sudah semester akhir, sayang klo pindah. tetap semangat, sebntar lagi lulus.
Apakah lulusan politeknik ini dapat langsung jadi pns seperti politeknik ikatan dinas yg lain ?
Utk lulusan tdk ada ikatan dinas utk mjd pns, tp akan dibantu prospek magang dan bekerja di dunia konstruksi (bumn, bums)