its the documents in which all the details of supplier has been mentioned.previous project covered by them also mentioned. Its a document like a company profile..
A nice informative videos. Please clear my below doubts Test reports for material is required? Please confirm we require third party testing certificate or we can approve material on the basis of Mill test certificate. Please Cleaify the MIR Process also.
Is the technical data sheet and testing, will be provided by the suppliers? I just started a new job, and my seniors don't want to teach me, and they always embarrass me every time I ask.
Technical data sheet containing all the technical data of material and prepared by manufacturers. Compliance sheet are for projects to compare data of specs with technical data sheet and prepared by supplier or project team sometimes
Sir I am working in Dubai villa construction as civil site engineer but want to become Q/C and Q/A Engineer how which course should I do from which institute and what the main thing that a qc and qa should know
السلام عليكم Good job I would like to ask you about if it is legally when i submit drawing for consultants and give me resubmit after i had finished i resubmitted he mention new comment is it legally ?
Valuables sharing
VALUABLE SHARING
Very Impressive Engr saib
Thank you so much for breif explination.
Thanks! Engineer 😊
Bro, I am really very much impressed by your video. This is really a good source of information.
Informative and useful...
Sir kindly explain Prequalification
its the documents in which all the details of supplier has been mentioned.previous project covered by them also mentioned. Its a document like a company profile..
A nice informative videos.
Please clear my below doubts
Test reports for material is required?
Please confirm we require third party testing certificate or we can approve material on the basis of Mill test certificate.
Please Cleaify the MIR Process also.
For some materials MTC is required and for some materials third party tests reports
Assalamualaikum
You make video on pre qualification
Tysm♥️ and it helps a lot
Is the technical data sheet and testing, will be provided by the suppliers?
I just started a new job, and my seniors don't want to teach me, and they always embarrass me every time I ask.
Technical data sheet and test report (FAT) will be provided by supplier
What is the difference between Technical Data Sheet and Compliance sheet as both sheets have material specs.
Technical data sheet containing all the technical data of material and prepared by manufacturers.
Compliance sheet are for projects to compare data of specs with technical data sheet and prepared by supplier or project team sometimes
@@CivilEngineerAtSite thanks alot
Hallo sir.
i realy want to understand, but its very difficult. best of lucks..
How
Sir.your video very very nice.sir can you make your video in hindi
What is pre Qualification of a company where to get this document
Please provide PDF of this
what is the difference between technical submittal form/ material approval request form / document submittal form
Same
What's meant by pre qualification of company or vendor?
Can u upload the document of Qc please
Sir I am working in Dubai villa construction as civil site engineer but want to become Q/C and Q/A Engineer how which course should I do from which institute and what the main thing that a qc and qa should know
compliance sheet comply section 3 45 000
Dear sir i am fresher Qa Qc Engineer on KNPC
السلام عليكم
Good job
I would like to ask you about if it is legally when i submit drawing for consultants and give me resubmit after i had finished i resubmitted he mention new comment is it legally ?
Yes he can comment on any revision any time
What is the role of civil inspector in KSA how do they work & plz share the best consultant working there
Materials and work inspection
@@CivilEngineerAtSite who will be prepared documentation like MAR, WIR, MIR, Method statement, ITP etc?
Please explain QC INSPECTOR role & responsibility?
what is difference between MAR and transmittals
Can u upload the document of Qc please