Time and Work || Memory Based New Pattern Questions from IBPS, SBI and RBI Exams

Поділитися
Вставка
  • Опубліковано 5 лип 2020
  • Do you like our videos? Then subscribe to our channel @ bit.ly/2GyZBjc and press the 🔔 Bell icon to get regular updates.
    This is an archived session conducted in last year. You may find some information given during the session are irrelevant. Kindly ignore those. In this session, you will find an explanation on examples of time and work problems has been explained briefly in this video of TalentSprint. Initially, these problems can make you feel confusing but proper methods to solve it will save your time and efforts. Examples explained in this video will give you a better understanding to solve these questions efficiently. These questions are an important part of the IBPS PO and other similar competitive exams.
    For more such videos, check similar videos like this: • Time and Work | Quanti...
    #CompetitiveExams #QuantitativeAptitude #TimeAndWork
    TalentSprint Aptitude Prep focuses on Quantitative Aptitude, Reasoning Ability, General Intelligence, General Awareness, Banking and Current Affairs. Our live sessions by the expert faculties guides you for various competitive exams. TalentSprint’s Aptitude Prep provides access to the best-in class videos that can help boost your chances of success in Bank, SSC and Govt Exams like IBPS, SBI, RBI, SSC CGL, SSC CHSL, SSC CPO, Railways, Insurance, Campus Recruitment and other Govt Exams. TalentSprint's Video and LIVE Program help aspirants get ready for Bank, SSC and Govt Exams from the comfort of their home. Learn from expert LIVE classes and videos along with Practice on latest pattern questions in real exam interface to Perfect your preparation for the hyper-competitive world.
    Follow us on Social Media: Facebook: / talentsprint Twitter: / talentsprint Instagram: talentsprint_ed...
    Happy learning!
    TalentSprint Aptitude Prep

КОМЕНТАРІ • 8

  • @saiprasadnakod1407
    @saiprasadnakod1407 3 роки тому +1

    You are one of the my favourite.

  • @saiprasadnakod1407
    @saiprasadnakod1407 3 роки тому +1

    Mam you are great

  • @sahanashanbhag4842
    @sahanashanbhag4842 3 роки тому

    thank you ma'am

  • @santoshisarakanam499
    @santoshisarakanam499 3 роки тому

    Good explanation

  • @subha9374
    @subha9374 3 роки тому +1

    Good level of qstns

  • @Noorit240
    @Noorit240 3 роки тому

    A can make 100 objects in 8 hours while B and C can do the same in 10hours and 12 hours respectively. All the workers started together at 9:00 am and stopped at 11:am. Rest was done by B and C. Approximately at what time will the making of 100 objects be completed? Please help me out

    • @sahanashanbhag4842
      @sahanashanbhag4842 3 роки тому +1

      by using men*time=constant concept:
      using 1st sentence:
      8A=10B => B=4A/5
      8A=12C => C=2A/3
      using 2nd sentence:
      (A+B+C)*(2hrs)+(B+c)*(Xhrs)= A*8 (or B*10 or C*12 since it's men*time required to complete task)( 2hrs since 9 to 11)
      (A+(4A/5)+(2A/3))*2 + ((4A/5)+(2A/3))*X =A*8
      => (1+4/5+2/3)*2 + (4/5 +2/3)* x =8
      solve and get x . X will be extra time required to complete after 11am.. add that obtained X hrs to 11 am to get the completion time... i hope it's correct