    @priyavarghese9618 Місяць тому

    Thank you so much sir ❤

  • @QSWORLD.
    @QSWORLD. 5 місяців тому

    Hi all , in variation process I had mentioned about clause 20.1 as notice , it is a mistake .. when explaining the eot confusion caused me to put that reference

  • @waseemmanaf6623
    @waseemmanaf6623 3 місяці тому +1

    Hi Midhun, what you presented is correct if an adjustment to time for completion is not agreed under CL 13.3. If time for completion is not agreed or initiated by the contractor under CL 13.3 he can still claim the EOT under CL 20.1 identifying CL 8.4.(a) as the course of action.

    • @QSWORLD.
      @QSWORLD. 3 місяці тому

      Thanks for the feedback

  • @imrajahmedpunekar1194
    @imrajahmedpunekar1194 5 місяців тому

    Then what is the correct clause for Sending the notice...clause#20 is for contractors claims

    • @QSWORLD.
      @QSWORLD. 5 місяців тому

      Same clause if variation , send a notification of variation