Delay events, such as unforeseen circumstances, weather disruptions, or equipment failures, can significantly impact a project's schedule. While these events are crucial to consider in overall project analysis, they are typically not included in the As-Planned vs. As-Built analysis for a specific reason: planningp6.com/why-we-dont-add-delay-events-in-as-planned-vs-as-built-analysis/
Great effort in putting this master piece..I have a question to ask.. While creating Delay Analysis, do we need to remove the Actual progress from the updated project schedule before we can initiate any method? because I can see that every Activity has NOT STARTED STATUS
What a fabulous content it gives a really pricey point to understand the basic things...
Thanks for the feedback.
Thank you for this. This is very informative and very well explain. Thank you so much for this content please continue sharing this kind of knowledge.
We are glad that it is beneficial to the public.
We appreciate your compliments and feedback; this is an ongoing process that will never end. *(In Sha ALLAH)*
Brother in this we dont want to add delay events in the p6 schedule?
Delay events, such as unforeseen circumstances, weather disruptions, or equipment failures, can significantly impact a project's schedule. While these events are crucial to consider in overall project analysis, they are typically not included in the As-Planned vs. As-Built analysis for a specific reason:
planningp6.com/why-we-dont-add-delay-events-in-as-planned-vs-as-built-analysis/
Great effort in putting this master piece..I have a question to ask..
While creating Delay Analysis, do we need to remove the Actual progress from the updated project schedule before we can initiate any method? because I can see that every Activity has NOT STARTED STATUS
Indeed, actual progress must be eliminated. On the other hand, using the approved baseline is the best practice.
Can you please send me this sheet
Send a screenshot of the document through WhatsApp, we will share it (If it is free)