Get started in Solar PV and Battery storage - Filling in G99 G98 and MCS - NAPIT training

Поділитися
Вставка
  • Опубліковано 25 жов 2024

КОМЕНТАРІ • 31

  • @ashpab101
    @ashpab101 4 місяці тому +1

    Very much appreciate the insight and explanation. Great video Mark!

  • @HollierElectricalContractors
    @HollierElectricalContractors 11 місяців тому +1

    Another fantastic vlog that gives one man bands an insight in the paperwork side of MCS. 👍

    • @electrician247
      @electrician247  11 місяців тому

      No probs mate. This next few videos are all about that. Ending with the installation and testing stuff. From the thick of the trenches trying to do it lol. Can’t get more authentic than that 😂

    • @HollierElectricalContractors
      @HollierElectricalContractors 11 місяців тому +1

      @@electrician247 looking forward to it.

  • @jchidley
    @jchidley 6 місяців тому +1

    Very well explained. I submitted an online fast track application to my local DNO, UK Power Networks, and the process was the same. As of March 2024 there stated response time was 45 days.

  • @lukekinchlea7996
    @lukekinchlea7996 11 місяців тому +1

    Perfect timing, I’m doing the course next week!!

  • @CommercialGasEngineerVideos
    @CommercialGasEngineerVideos 11 місяців тому +1

    There's so many things you can do. I reckon I could be on a course every week of the year. Will look up some solar courses😢.

  • @markbennett9043
    @markbennett9043 11 місяців тому +1

    Awesome looking into this now. Will watch later

    • @electrician247
      @electrician247  11 місяців тому

      Hope it’s useful Mark

    • @markbennett9043
      @markbennett9043 11 місяців тому

      Want to do DIY install then get spark in for connecting up new bidirectional meter. Emailed Local dno reckon I can have a 6kw inverter. Trying to keep costs down.

    • @electrician247
      @electrician247  11 місяців тому

      @@markbennett9043 ahh assumed you were an electrician lol. Without the MCS you will do well to get an export mpan. Also ensure you notify local building control. Both those carry not insignificant cost and without them carry substantial fines and other liabilities.
      My general advice would be to consult a reputable installer as these kind of works go beyond DIY imho.

    • @UplandsJack
      @UplandsJack 11 місяців тому +1

      Hi Mark enjoying the video as always…
      I did the Bpec 5 day course (solar & battery storage) and exam 18 months ago but apart from helping another spark do his own set-up.
      Reason for not taking it any further is purely the cost/time getting the MCS.
      With that said, I’m sure Ive read that you no longer need to be mcs registered since Aug 23 to get octopus and other suppliers G-99 /G100 applications?
      Can you advise if this is correct.
      Will now enjoy this video

    • @electrician247
      @electrician247  11 місяців тому +2

      @@UplandsJack kind of is the answer lol. I can only speak as regards octopus as that’s the one I looked into. But you still have to apply to them, pay a fee, notify building control, DNO, warranty etc.
      Essentially it’s the same thing but imho harder to process and no lower cost if you do a few jobs per year.
      We haven’t been able to make use of it anyway so can’t comment beyond that.
      I believe octopus have a scheme of their own on the way similar to MCS.
      The MCs process has got lots simpler in itself no need for hies or recc anymore.
      I summarise it like the part p cps stuff. Yeah we can save our fees and just notify jobs via local building control. But that ends up harder work and more expensive. This is just the same, MCS is easier and cheaper for us. Plus we get a fair few enquiries over from the MCs website itself and consumers are asking for it!
      Hope that helps and good luck getting going with it mate

  • @grahamdaniel6035
    @grahamdaniel6035 8 місяців тому

    Hi, have you ever filled in CLS form part of G100/2 application form for limitation metering?
    Confused with the question:
    Aggregate sum of all loads (including storage) in the installation (ie controlled by the CLS and those that are not controlled by the CLS).
    Does this mean other loads on DB like shower, ev, sockets?
    Thanks

  • @amiraghazadeh6197
    @amiraghazadeh6197 6 місяців тому

    Hi Mark. Thanks for this tutorial. I just have a question. We have a 2-MW renewable connected to an 11-kV distribution network. The connection to the 33kV network is a demand connection, which means we are only allowed to import from the upstream network. Now, we want to get permission from our DNO to export to the DNO's network. The DNO allows a modification to the existing connection agreement to allow for export capacity. Now my questions are what would be our approach step by step? Further, what are the necessary compliance steps that you need to follow?

    • @bramcoteelectrical1088
      @bramcoteelectrical1088 4 місяці тому

      Need to contact a decent electrical enigneer or speak to a g99 panel building company see if they can offer some help.
      Complex one this 👌
      I worled on solar parks as enginner

  • @ianviscogliosi5533
    @ianviscogliosi5533 Місяць тому

    Hi Mark, been following you for a while now & this video caught my eye. I have a consumer question for you. I have a Givenergy 3.6 Gen 1 Hybrid inverter, with a 4.1kW array & 13kWh battery storage. I have been toying with the idea of replacing the Gen 1 with a 3.6 Gen 3 unit. Does the DNO need to be informed i.e. another G98 notification? Also, what if I installed a 5kW Gen 3 (which is not that more expensive) I assume my installer would have to make a complete G99 application? Thanks…. Ian

    • @electrician247
      @electrician247  Місяць тому

      Excluding any FIT elements you wouldn't be required to notify the dno if the rating remains the same. Just ensure it is ena approved. If you have a FIT you will need to inform them of any maintenance for approval. If going to 5kW yes you will need to do a G99. Hope that helps!

    • @ianviscogliosi5533
      @ianviscogliosi5533 Місяць тому

      Thanks for the rapid reply Mark. I’m on Octopus out going light, so I will need to inform them. I’ll speak to my installer & ask him if is prepared to do the swap to 5kW.
      Thanks again …. Ian

  • @davidianwalsh
    @davidianwalsh 8 місяців тому

    Have you installed a pair of the GivEnergy AiO batteries yet? I’m assuming that they along with a solar inverter would be above the 60A limit mentioned?

    • @electrician247
      @electrician247  8 місяців тому

      Not currently a supported option by the manufacturer so no. But it is coming very very soon 🤩

  • @NathanJones-cq1dz
    @NathanJones-cq1dz 4 місяці тому

    Hi, I have recently ordered panels and solar from EON and I need a G99 for exporting. I have been told that the install cannot be booked until the G99 has been received however another installer has stated that I can install the solar but cannot recover and SEG payments until the G99 has been released. Are EON correct as I would like to benefit from solar despite the SEG while the sun is still shining?

    • @electrician247
      @electrician247  4 місяці тому +1

      It’s a grey area in terms of connecting equipment. If it is ENA approved one argument is you should be able to connect anything you like within the existing supply capacity. Another angle on that is you need agreement to export power into the grid as you can effect voltages in the local area.
      Our approach is the same as eon we will not install equipment than export beyond a G98 level without prior approval. You could install and limit the export to within g98 limits during the application but again that is grey lol.
      All that said G99 applications are usually faster than the lead time on an installation in any case. I would also advise some shopping around beyond energy suppliers as value is not always best delivered in those places.

  • @BenCaird
    @BenCaird 10 місяців тому +1

    So I had my first g99, and the dno is asking for loop impedance. Says needs to be less than 180mohms. Im using an MFT pro. Did the ZS at the main switch of the solar CU and got a reading of 0.10ohms. Would you just fill in 0.10 ohms or converter it to mohms, so 1.0E-7 MΩ? Sorry if this is a stupid question just out my time 6 months and my background is commercial/industrial.

    • @electrician247
      @electrician247  10 місяців тому

      Is this asked for on the commissioning data? Or pre install?
      If commissioning it’s just the Zs at the solar inverter. So long as you denote the value it shouldn’t matter what form you send it in. 0.10 is a good value!

  • @andrewraine8207
    @andrewraine8207 9 місяців тому

    How much does the g99 FastTrack approval cost from Northern Power Grid?

    • @electrician247
      @electrician247  9 місяців тому +1

      The process is free. The outcome if work is needed to connect equipment varies massively

  • @markrainford1219
    @markrainford1219 12 днів тому +1

    How many sparkies are put off just because of the mountain of red tape? Are the DNOs really interested in the battery chemistry of a domestic battery, I mean REALLY?

    • @electrician247
      @electrician247  12 днів тому

      Lots most likely. The DNOs don't care in terms of chemistry in and of itself. But that does play a part in potential energy output which is why they ask for the data.

  • @zjzozn
    @zjzozn 10 місяців тому +1

    Like 👍