Estimation - One Room (2021)
Вставка
- Опубліковано 1 січ 2018
- To estimate the cost of any building or a structure, drawings, specifications and rates are required. Regarding the detailed estimate by long wall and short wall method and centre line method, the drawings consisting of plan elevation and section are sufficient.
#Buildingestimation #Civiconcepts
Follow my Facebook page : / civiconcept
Thanks guru ji Aapka smghane Ka trika mast hai
Very Nicely You have explained Dear Engineer Sb. May you always stay blessed
Best ever best explaination ❤
Sir, I want to construct one simple 10x12 long lasting cement block room in farm without column. With two windows and one door. Too many thefts happen so things should be strong. Please suggest idea, which materials to use and what may be total cost
Sir platesr work kese cacluate kre
Very good lecture thank you soo much sir
Sir you are outstanding
sir 1 step mai length same ku rahi....as same as in excuvation
this calculation for only foundation or Full room up to Uper Beam?
clean explanation sir
Thank you
nice bro keep it up
Sir kisi v wall ka estmat and casting kaise kre
Bhai 14×12room rcc kitna karcha ata he plz guide me
pl continue u estimate for one room, very good explaint
approximataly kitana hoga,,&this plan includes load bearing str. slab provided
Very nice sir
Nice vedio # civilstudy
Thanks
Thanks 😊☺️👍🙏
13/15fit bed room re support pain kichi calom dabaku padiba ki
I don't know why are u putting steps under foundation area like bricks but when we construction we don't use like that steps
We take 200mm extra on either side of the pcc bed for excavation , which gives 0.9+0.2+0.2 = 1.3
Sir yahan length find karne keliye what didn't we use the formula L= CL- width/2 × no.of T junction???? Pliz explain....
There is no t junction here
Total length exacavation hota hai kiya? Or numbr of post excavate hota hai.
Very good bro👍👍👍
Thanks
bhai hama plan main centre line Q draw khrne hai kis maksad k leyei
Sir please clear the concept of estimating the building with walls of different thickness and with different foundation, all the videos are made with only 1-2 similar examples, no one is moving ahead of these things
Deduction methods estimating p/z explain in breify.
septic tank rectangle circular video karo bai
Door window deduction to kr dete?
I hv subscribed you channel
sir please tell me about with mortar volume how many bricks are used in
the given plan
Sir HSR ke according bhi ek video bnaiye
tamil laungage full building estimate sir plz
Sir y center k bhar wali distance add krni hogi pecche
Becoz we calculated c/c for 0.3 wall, pcc width is different so we required correct it
You not add P.c.c.
Only this
Please more detail like
Dpc
Shuttering work
Steel cutting bending fixing
Rcc concrete on slab
Plaster
Rcc flooring
Electric work
White wash
video available on channel please check
Thanku u sir....very helpful
Sir thank you so much for this video....Simpson rule and trapezoidal rule k math k under 1 video ho to acha hota plz sir...
Tell me center line method
So what about door and window
Watch other video for detail Estimation
Sir video m down se apne channel ka logo jata diya karo video dekhne m problem hoti h
Sir wall 0.3 kaisa hotha sir 9 inch wall ka 0.2 hothans
0.3m = 9 " approx
Sir jis room ki foindation m offset one side hote h uska kaise krenge bataiye sir
@7.51 m ek chiz glt h
It will be 19.2 x 0.60x 0.20 = 3.456
Sir make a video how to estimate bulding center line method
Please give me plan elevation and section n also Footing details plz plz
Estimate of victory tower in hindi
Double room ka sir uploaded kijije sir
Aur video hai channel subscribe karo
Can't say . (point) fifteen... always use to say point one five
sir eartwork and pcc k but next step sir
see my other video
bro send me junction video of this tuttorial and also tell me how to calculate the bricks of well
Chapter 3ka hindi
Thanks😭
Supper
2 wall ko nikalne liy
Thanks sir
aapki awaj bahut slow aata hai plz thora sa apna volume badha dijie
Bro pls video update in Tamil language
Are bhai window deduction to kr
Frd.. Its quantity up to ground level..how can i deduct window
sir 10*10 room ka kharacha kitana aayega
Locally material rate and labour rate par depend karta hai
just copying others simple qs. please bring something new :/ more advance
Teaching in Indian but seeking subscribers is done in English😂😂😂
Very nice sir
bhai ye toh basement ka method hai hame sirf ek jageh excavation karke column dena hai puura wall dig ni karni
Its load bearing structure not frame structure
explain about frame structure if u can..
U hve to calculate qty for columns footing and multiple with no. Of columns in building