200 Ultra Hard PMP Questions 101-110

Поділитися
Вставка
  • Опубліковано 30 лис 2024

КОМЕНТАРІ • 22

  • @martinkearns2889
    @martinkearns2889 2 дні тому +1

    Watched the first 100 Q&A series of videos, but now only here to confirm that I passed my exam yesterday scoring AT/AT/AT. There can be no doubt that these videos and the Udemy PMP course is invaluable in preparing for the PMP exam. Thank You Andrew!

  • @karnick6500
    @karnick6500 3 дні тому +1

    Thank you Mr Andrew

  • @rachelee1031
    @rachelee1031 2 дні тому

    Hi Andrew, I passed my PMP exam yesterday. Thanks for sharing all the great contents.

  • @karrarengr
    @karrarengr 3 дні тому

    Hi Andrew, I have passed PMP exam last week. Thanks for ur simplified lectures

  • @sadaneltigani1459
    @sadaneltigani1459 3 дні тому +1

    Much apprecaited

  • @kellysworld4329
    @kellysworld4329 3 дні тому +4

    For question 106, I didn't think "A" would have been the answer, maybe cause of the wordings. I would have expected the wordings to be something like, "Organize intermittent "virtual" gathering ......'
    But with the current wording, it sounds as if to organize a gathering where every team member will colocate (which is not possible due to team members being dispersed in different geographical locations).
    Just my thought

    • @BryantInManila
      @BryantInManila День тому +1

      I have exactly the same thought, unless the project has the budget and time for intermittent collocation - hence B was my answer

    • @adwoacarr
      @adwoacarr День тому +1

      definitely the wording because even reading within the context as he mentioned still would not yield the answer A

  • @nishikantwairkar6866
    @nishikantwairkar6866 2 дні тому

    7/ 10 , my scores r getting better da by day, thanks to you sir

  • @elhamboostani8718
    @elhamboostani8718 2 дні тому

    9/10, Thank you very much Andrew. Your tips helped me a lot, I appreciate it. You are wonderful!🙂

  • @zavianwilson6070
    @zavianwilson6070 3 дні тому

    In question 101, please correct me if I'm wrong, the root cause of the problem was identified and explicitly stated by a key stakeholder as "missing requirements, an impact analysis"
    Wouldn't carrying out the analysis the best course of action?
    After all, OPA stated in answer two is not necessarily a 'project management plan' so to speak.... Furthermore, i4 was also sited in the question stem that the agency provided funding previously upon receipt of a similar assessment of sorts...
    Please advise... In my opinion, B was a better course of action.

  • @Kreative_weirdo
    @Kreative_weirdo 16 годин тому

    Hi Andrew, I saw question somewhere related to business environment, and i was not satisfied with the answer they said was right. Here is the question: Following a re structure in your organisation, the agile team will loose 3 members from its 9 membered team. The sponsor has asked the project manager to still complete the project on time. What is the best course of action for the project manager?
    A. Work with the stakeholders to prepare a new roadmap to meet the original project completion date with reduced scope.
    B. Alternatively assign the other team members to work overtime.
    C. Re distribution of tasks among other team members to work overtime to meet the original completion date.
    D. Create and update issue logs for instance where planned work is not completed due to reduced resources.
    Could you please let me know what answer do u think is best and why?

  • @abhinavsrivastava8140
    @abhinavsrivastava8140 3 дні тому +2

    84/110

  • @swimswim287
    @swimswim287 2 дні тому

    @10:57 Q105.) Why is the answer marked in red as "A" but explanation it gives is for answer "B". (I chose answer B too)

  • @karrarengr
    @karrarengr 2 дні тому

    Andrew, from where i can find project documents templates for practical implementation in projects. I need sample project management process documents

  • @hassanrs
    @hassanrs 3 дні тому +2

    For question 102, the correct answer is C but why does the explanation at the bottom of the screen after the answer is revealed is about choice B (external consultant)? 🙃

    • @BryantInManila
      @BryantInManila День тому

      Same in question #105, explanation refers to B.
      Then....I ran the question in ChatGpt, Gemini, and Perplexity, they all answered C. 😮
      I am now confused 😢

  • @lucialouw6670
    @lucialouw6670 3 дні тому

    Dear Sir
    Is there also questions for capm?

  • @jdsk8914
    @jdsk8914 3 дні тому +4

    Thanks Andrew...I passed my PMP exam 💪🏽
    Time for some cake and Red Stripe.
    Your course is awesome !

    • @zavianwilson6070
      @zavianwilson6070 3 дні тому +1

      The great Jamaican lagger!

    • @jdsk8914
      @jdsk8914 3 дні тому

      @zavianwilson6070 From the heart of the Caribbean !! 🍻

  • @muratkazanova5537
    @muratkazanova5537 2 дні тому

    8/10