It's Time for 10 More PMBOK 6 Questions and Answers (21 to 30)

Поділитися
Вставка
  • Опубліковано 30 вер 2024

КОМЕНТАРІ • 24

  • @gokhangoker8633
    @gokhangoker8633 Рік тому +2

    👏👏 Thank you David for your effort, your half an hour question/answer videos are really helpful

  • @danaebarnes8082
    @danaebarnes8082 Рік тому +1

    Truly fantastic stuff- thoughtful explanations that help me uncover the question logic and identify the best key words to focus on. Appreciate all the hard work, super helpful vids to prep for the PMP test!

  • @b_aleeya_z4415
    @b_aleeya_z4415 Рік тому +1

    Thank you so much David for sharing these videos. Fantastic learning sessions 💯👏

  • @manjunathbhixavatimath150
    @manjunathbhixavatimath150 Рік тому +2

    Hi David ..I don't seem to agree on Q 23. The scenario is about qualitative analysis and there they would not know what part of contingency to be added to come up with the worst case. I think we should be doing option 3 there so that we get a hold of it for allocating contingency reserve.plz clarify.

    • @amerchant1215
      @amerchant1215 Рік тому +1

      Contingency reserve is used when risk has occured, as the question states. The question asks 'What will you do next?', so the first thing to do for this situation would be to review or create risk response in the risk register. Risk response is planned after performing qualitative and quantitative risk analysis. So again, the first thing to do is to review if risk response has already been created or create one. Option B is correct

    • @davidmclachlanproject
      @davidmclachlanproject  Рік тому +1

      You raise a good point, and good discussion here too! Quantitative analysis would help narrow options down or prioritise the highest risks. As the risk has already happened, however, it's time to respond to it, and we do that with the contingency reserve 🙂

    • @sumitmitra7336
      @sumitmitra7336 Рік тому

      @@amerchant1215 very clearly explained by you.. Great

    • @ruslankapustin3954
      @ruslankapustin3954 14 днів тому

      Dear ​@@davidmclachlanproject,
      I have a question regarding the use of contingency reserves in risk management. How can we determine the appropriate contingency reserve without first performing quantitative risk analysis? Typically, we would need to quantify the probability and impact of the risk to calculate the reserve accurately. If the quantitative analysis hasn't been completed, how do we know the correct amount of reserve to allocate?
      Thank you for your clarification!

    • @ruslankapustin3954
      @ruslankapustin3954 14 днів тому

      Question 23 does not indicate that the risk has already occurred, it was only identified.

  • @tammybenaytv4631
    @tammybenaytv4631 Рік тому +1

    Thank you, David. I did ok this time. I got 8 right. I didn’t get 7 or 8. But I think those questions were so specific to the PMBOK that it was hard to use process of elimination. Number 3 tripped me up a bit too. I wasn’t sure if we were to use contingency reserve if haven’t done the analysis to see how much it cost first. But I guessed right.

  • @pranayrai4199
    @pranayrai4199 11 місяців тому

    Question 29, option B, is a "plan," not a "process."

  • @nareshsem333
    @nareshsem333 Рік тому +1

    Thanks David your effort are really fabulous always, love you❤

  • @kchandrashekar35
    @kchandrashekar35 5 місяців тому +1

    These questions are made me very impressive

  • @swolezerow18
    @swolezerow18 Рік тому +1

    the last one it was impossible... really!

  • @Wondi.Hailes
    @Wondi.Hailes 11 місяців тому

    As for Question #23, I thought we have to perform first qualitative/quantitative analysis prior to respond the risk. For that, I had chosen option "C" and the next activity would be "B". Am a bit confused in here..............

  • @kchandrashekar35
    @kchandrashekar35 5 місяців тому +1

    08 out of 10

  • @mohamedgahayr7419
    @mohamedgahayr7419 Рік тому +1

    david do you always add 10 question for every week?

    • @davidmclachlanproject
      @davidmclachlanproject  Рік тому +2

      I have a few in the backlog, so trying for at least two videos (10 questions each) a week until I run out 🙂

  • @justin9605
    @justin9605 9 місяців тому +1

    Thank you.

  • @ashenafimulubrhan828
    @ashenafimulubrhan828 Рік тому +1

    Thanks for your effort!!

  • @rajeshsingh-dl8fj
    @rajeshsingh-dl8fj Рік тому +1

    Thanks for sharing

  • @brahmiimen3804
    @brahmiimen3804 8 місяців тому

    Thank you :)

  • @Vihaan1907
    @Vihaan1907 Рік тому

    Hi David, I don't agree to the answer of question 30, procurement strategy should be decided first thing after deciding that work be outsourced , which includes (Delivery methods, contract types and procurement phases) , so option B is the correct choice. page 476 PMBOK.