Difference between Metering CT Protection CT,5P20,Class 1 and 0.2-? in Tamil
Вставка
- Опубліковано 1 гру 2024
- Difference between Metering CT Protection CT,5P20,Class 1 and 0.2-? in Tamil
CT basics version-1
• Current transformer wo...
CT burden calculation version-2
• Current transformer bu...
Why CT Should not kept open at load condition version-3
• why CT Secondary shoul...
In this video Current transformer name plate details are explained in Tamil
1.Purpose of protection CT
2.Purposes of metering CT
3.How to identity the metering & protection CT
4. 5P20 means what?
5.Class 1,0.5,0.2 means what?
6.why we use different types CT for metering and protection
7.Can we use metering CT for protection?
8.Can we use protection CT for metering?
facebook link : / generalengineeringtamizh
Instagram link : / msaranraj07
#MeteringCT#ProtectionCT#5P20#
Sir...., neenga semmaiya class yedukareenga..., vaazhthukal
Sir. 1% x 10A = 0.1A. So if current is shown as 10A then current is between 9.9A and 10.1A
Very useful thanks uploading 👍
Thank you...
Thanks for the short and sweet presentation.
Still have a doubt in accuracy class for Protection and measuring CT's.
Share your doubt.....we will learn mutually...
Super explanation....
Thank you....
Very useful video sir thank you
Thank you...
Errors of ct விளக்கமாக ஒரு வீடியோ போடுங்க நண்பா👍👍👍👍
Will soon nanba...
Good class tq sir
Super sir
sir can u explain by video what happen if we use different class for overhead line..substation A using CT class X..but another remote end substation using CT class 5P20..what happen if fault occured..??
Super bro
Sir please explain ( CT POLARITY AND IMPORTANT OF CT STAR POINT CONNECTING TRANSFORMER LINE PROTECTION)
Please tell me about "PS CORE" sir , what is the use of PS core ..?
PS class stand for special protection like REF and differential protection
Sir, Please make video on Hindi/English language,Where everybody learn that.
Thanks electrical drawing reading video pannunga
Will soon...
0.2 error na 9.8A Or 10.2A thana varum.Neenga 9.98 or 10.02 nu solirukinga apo 0.02 error mathiri meaning varum.
Name plate illaina epdi identify pandrathu
Hai bro,
We are using both metering and protection CTs in series ( at same feeder). So at the Fault time, how the metering CT behaves ? Is it get saturated?
Another doubt, what happens to metering CT if protection not operate during fault ..
Protection CT's are designed to have small error during fault condition ,so that they can be Correctly reproduce the fault current for satisfactory operation of protective relay ...
The protective CT's should not saturate upto 20 to 50 times full load current
Sir yapdi ratio va choose pandrathu
Based on requirements....
Please upload breaker CRM USES
After posting VCB video will plan for breaker testing like CRM,dielectric test....
@@generalengineering1194 done 👍
Ct la irukura 1600/5a ku meaning enna itha yapdi yantha ratio va choose pandrathu please konjam sollunga
My mail id bjmsvvignesh@gmail.com
Already we made a video for this topic...
Videos available in our playlist....
@@generalengineering1194 s I seen thanks a lot
@@generalengineering1194 bro one more doubt capacitor stage yapdi decided pandrathu
👍
And different between sensors and switches in tamil
inductive and capacitive proximity sensor videos are available in our playlist....
Basic difference between sensor and switch
Sensor-Non contact sensing device
Switch-Contact sensing device
@@generalengineering1194 thanks
Bro AVR PATHI SOLLUNGA
Will do soon nanba....
Waiting bro
20 percentage aaa 20 times aaaa sir
20 times...
0.5s class explain pls ?
Even below 1% of load, CT ratio error will not exceed 0.5%. 0.5S class CT will use for sensible metering circuits
10.1A r 9.9 A