As the vendor calendor can be deleted from the po, is it also possible to overwrite the transport days for an order ? It seems that the calculation of the date can not be overwritten.
Yes, they cannot be directly overwritten. Transport days are controlled by ship-to warehouse on PO line. Either change the warehouse or update PO transport days in a new form.
Questions 1. How this date calculation will work with Master planning. Will Requested receipt date auto calculate during the firming of Planned purchase orders? 2. How the Confirmed Ship date will work with Landed cost. Will Confirmed ship date auto update when 'Tracking' is updated in Voyages
Good questions... #1 yes, it will, based on requirement date on planned PO. #2 this will need to be tested. Would appreciate if you can update us with your findings.
Very useful with your short demos 👍👏
Loving these short videos!
As the vendor calendor can be deleted from the po, is it also possible to overwrite the transport days for an order ? It seems that the calculation of the date can not be overwritten.
Yes, they cannot be directly overwritten. Transport days are controlled by ship-to warehouse on PO line. Either change the warehouse or update PO transport days in a new form.
Questions
1. How this date calculation will work with Master planning. Will Requested receipt date auto calculate during the firming of Planned purchase orders?
2. How the Confirmed Ship date will work with Landed cost. Will Confirmed ship date auto update when 'Tracking' is updated in Voyages
Good questions...
#1 yes, it will, based on requirement date on planned PO.
#2 this will need to be tested.
Would appreciate if you can update us with your findings.
Following the questions of @n1k1i1 how does this work with the Landed Cost function ? Needs to be tested as well...
Lol with the zip code 90210
Yes, Beverly Hills :)