  • Now that construction has started on the Vista Lago Plot we will be posting monthly updates on the progress of the works. This update focusses on the retaining walls which will be supporting the houses and roads. Work on these walls have now reached the final stage and in a week or two they will be sprayed and sealed with concrete. It takes approximately 3-4 months to complete these kinds of walls. Once the villas are built these walls will not be visible.
    For more information on Vista Lago Residences, visit the Vista Lago page on the BRIGHT website: by-bright.com/...
    You can also email the Sales Team on info@by-bright.com or call them directly on: (+34) 648 981 111