@@fas-yt765 There is no excel for importing the activities but an exported spreadsheet. Please follow the video and try. You might be doing a mistake. Otherwise send me screenshot of the error.
Thanks for sharing the knowledge, however, How can we apply the VLookup if we have the same WBS name (Block 1, Block 2 etc...) in different project phases?
This was amazing as usual. But I am wondering what extra step I need to take if I need to upload all activities but under multiple wbs not just one wbs.
Gud Mr. IRFAN I m regularly viewer of your UA-cam video on P6 sch. Which help me lot to learn more and thanks for your informative video I need video on activities relationship from excel to P6 as u said in one of your Video I request for you urgently assistance Thanks in advance Alhz MUNAWAR
@@projectplanningtacts5330 yes please if you can prepare a tutorial. To see how multiple boq items are to be linked with one activity. Or how to distribute a % of one boq price among multiple activities.
It's very easy, but when I try to follow the procedure. I get error command : control_updates_flag is null Task activity! Can you explain why it's coming and how I can get rid of it!? If I add number of activity in p6 and then export the file into xls and define the wbs code then the import is showing result in p6 How to avoid this. Here I can't get the user define activity code.
Are you trying to import activities or you would like to add WBS against the activities? If you want to add activities under the WBS which is in the project then you follow the process and get it done.
Dear Irfan,
Waiting for your valuable videos for quite few months. Please commence again.
Amazing 😁
Thanks ❤️
Nice .. very much useful Irfan.. thank you.
You're welcome Dear
excellent brother
Awesome work man....I appreciate ur work...I know ow tough it is to create a video while working.
Keep going.waiting for next video.❤️👍
Thank you dear.
It's showing some error to me .I tried a lot of times still error.is there any excel copy on it.if there plz send to my mail id farnas.ap@gmail.com.
@@fas-yt765 There is no excel for importing the activities but an exported spreadsheet. Please follow the video and try. You might be doing a mistake.
Otherwise send me screenshot of the error.
How can I send screenshot in comments
@@fas-yt765 projectplanningtacts@gmail.com
Good video
Thank you
Thanks for sharing the knowledge, however, How can we apply the VLookup if we have the same WBS name (Block 1, Block 2 etc...) in different project phases?
Thanks. There are different ways to do that. All you need is a unique reference to apply VLookup. Activity ID is always unique.
This was amazing as usual. But I am wondering what extra step I need to take if I need to upload all activities but under multiple wbs not just one wbs.
Process will remain same. You need to make sure while importing that the WBS code assign to the activity which is relevant to it.
@@projectplanningtacts5330 got it thanks
Thanks so much,, Can you please provide the link of the third tutorial (Assign relationships) !
Hi John
Here you go
ua-cam.com/video/Y9cm--lXjY8/v-deo.html
Gud Mr. IRFAN I m regularly viewer of your UA-cam video on P6 sch. Which help me lot to learn more and thanks for your informative video I need video on activities relationship from excel to P6 as u said in one of your Video I request for you urgently assistance Thanks in advance Alhz MUNAWAR
Thank you, Excellent Work.
Brother Could you please create BOQ format and cost loading in excel with the easiest way and import to Primavera
I will prepare a Tutorial video as per your request soon. Thanks
@@projectplanningtacts5330 yes please if you can prepare a tutorial. To see how multiple boq items are to be linked with one activity. Or how to distribute a % of one boq price among multiple activities.
Sure..it increases productivity....
Thanks for your feedback.
@@projectplanningtacts5330 ...Hope you are good...Excited for your next....
Thanks for your great effort, but please we need video for loading activity RELATIONSHIP from excel tp primavera p6, ASAP
me too,. about relationship of the works,. and if you have knowlege about oil and gas please share to us,. thank you
@@najebamrodin1350 any updates?
It's very easy, but when I try to follow the procedure.
I get error command : control_updates_flag is null Task activity!
Can you explain why it's coming and how I can get rid of it!?
If I add number of activity in p6 and then export the file into xls and define the wbs code then the import is showing result in p6
How to avoid this.
Here I can't get the user define activity code.
Are you trying to import activities or you would like to add WBS against the activities?
If you want to add activities under the WBS which is in the project then you follow the process and get it done.
salami