Brother, u said we have to assign dummy cost resources for both file, baseline and updated right? When i assign dummy cost resources for baseline file, the finish date is changed. How to solve this issue?
Kindly modify the settings before assigning the resource you added. Specifically, change the Duration Type to Fixed Duration setting for all activities. If you are still experiencing perplexity, please do not hesitate to reach out to us via email or WhatsApp.
It is very informative video and productive video. It has cleared the concept
Thanks for the feedback and Compliment.
We are glad to hear that our content has been helpful to our friends and viewers. We appreciate the feedback, please share our content on LinkedIn and other social media platforms with others.
Remember to mention @planningp6 and #planningp6 and planningp6.com
Hello and Thanks for sharing my bro!
Thanks for the feedback and Compliment.
We are glad to hear that our content has been helpful to our friends and viewers. We appreciate the feedback, please share our content on LinkedIn and other social media platforms with others.
Remember to mention @planningp6 and #planningp6 and planningp6.com
Brother, u said we have to assign dummy cost resources for both file, baseline and updated right? When i assign dummy cost resources for baseline file, the finish date is changed. How to solve this issue?
@planning-P6 yes kindly address this issue plzz
Kindly modify the settings before assigning the resource you added. Specifically, change the Duration Type to Fixed Duration setting for all activities.
If you are still experiencing perplexity, please do not hesitate to reach out to us via email or WhatsApp.
Assalam u alaikum sir I want to learn about planning engineering m working on infrastructure projects.
Plz share me the contact number
Walaikum Assalam
WhatsApp: wa.me/923088663797?text=Hello%2C%0A%0AWelcome%20to%20PlanningP6
Web: planningp6.com/
Email: Info@Planningp6.com