I had lots of these today in a schedule I was rebuilding for someone else, the logic was abysmal, no thought into a common approach at all. Good video though, thank you
Hi Micheal, how do I extract overlapping / clash activities for example between Construction and Commissioning. There are areas on the Project where Construction cannot work because the Commissioning team are working, and vis Versa.
In these circumstances, it's crucial to ensure that the relationships we establish between activities are accurate. If you believe that certain construction activities cannot commence until commissioning is completed, please add a finish-to-start relationship from commissioning to construction activity.
We actually don't want to do this. If we linked up everything properly then, have correct durations, then the critical path is true - we don't mess it. If you think it's incorrect, check your linking and durations.
I've got a question, how can we assign a virtual resource to all activity as a weight factor to see the project's s-curve, I mean wee preserve the current resources and cost, just add this virtual resource and see the result without affecting these two types of resources on eachother. Please don't hesitate if you need any further information, many thanks.
You can define a resource named "Virtual Resource" and assign it to all activities. The resource type can be either Labor or Non-Labor; just ensure that the standard rate is set to zero. After assigning it to all activities, add your specified weightage in the resource's budgeted unit section. You can then view the results in the resource assignment tab by filtering activities based on the assigned resource.
Need to learn P6? Check out the best Advanced P6 Training Available online:
www.planacademy.com/
Thank you Michael
Love the new style of video, Michael
I'm proud of you,thanks for your support to us
You're a great teacher. God bless you
can you upload videos related to delay analysis using primavera P6 and the concurrent delay analysis
Thanks a lot, Michael!
Quite helpful Video
WHY MY SCHEDULE PERCENTAGE & PERFORMANCE PERCENTAGE COMPLETED IS NOT ROLLING IN WBS & AT TOTAL
Thanks a lot. That was quite efficient to track the error!
Thanks Michael for this helpful explanation... very clear. Muito obrigado👌
Please can u share way to import activity realationships from excel to P6
I had lots of these today in a schedule I was rebuilding for someone else, the logic was abysmal, no thought into a common approach at all. Good video though, thank you
Hi Sir. Please make a video on how to make a recovery schedule. Please it will be highly appreciated
Hi Micheal, how do I extract overlapping / clash activities for example between Construction and Commissioning. There are areas on the Project where Construction cannot work because the Commissioning team are working, and vis Versa.
In these circumstances, it's crucial to ensure that the relationships we establish between activities are accurate. If you believe that certain construction activities cannot commence until commissioning is completed, please add a finish-to-start relationship from commissioning to construction activity.
Thanks Michael
If I understood right have I install Primavera P6? What version and where I can do it? Thx
SO HELPFUL
Hi
Could you pls. Guide me how to reduce the no. Of critical activities
We actually don't want to do this. If we linked up everything properly then, have correct durations, then the critical path is true - we don't mess it. If you think it's incorrect, check your linking and durations.
Thank You!
I am using P6 2023 and I cant change my start milestone to have a FS relationships with my second activity. How do i fix it?
Yeah - that's newish. A start milestone can't do a F-S relationship anymore. Just use S-S.
I've got a question, how can we assign a virtual resource to all activity as a weight factor to see the project's s-curve, I mean wee preserve the current resources and cost, just add this virtual resource and see the result without affecting these two types of resources on eachother. Please don't hesitate if you need any further information, many thanks.
You can define a resource named "Virtual Resource" and assign it to all activities. The resource type can be either Labor or Non-Labor; just ensure that the standard rate is set to zero. After assigning it to all activities, add your specified weightage in the resource's budgeted unit section. You can then view the results in the resource assignment tab by filtering activities based on the assigned resource.
Hi,