MAGKANO MAGPAPALITADA NGAYON? PLASTERING LABOR.
Вставка
- Опубліковано 21 жов 2024
- PAANO MALALAMAN ANG PRESYO SA PAGPAPALITADA.
This video is NOT sponsored. Some product links are affiliate links which means if you buy something we'll receive a small commission.
BUILDMATE: invol.co/cl5y7rd
Buildmate Online Depot
Welcome ka dito Ka-BUILDMATE! 👋
🚧Your One Stop Hardware Shop is always here
with the most complete home & living needs.
Be updated with our Special offers because every day
is Guaranteed LOWEST PRICE with us 🎉
✨DAILY VOUCHERS GIVEAWAY with just one click
in our ✅FEED Section & Chat button.
plus our Special 🚛 FREE SHIPPING deals
What are you waiting for?
Follow us and Get a Voucher now!
SHOPEE: Lowest hardware price (Buildmate Online Depot ) invol.co/cl5ta7h
Home improvement design: invol.co/cl5lx7p
LAZADA: Online Shopping Platform: invol.co/cl5lx98
Shop Online Specialized in hard to find items: invol.co/cl5lxab
The Ultimate online shopping Experience: invol.co/cl5lxdb
Thank you po sa malinaw na explanation ninyo. God bless you po!
Ang galing ner salute
Salute sir ,, detalyado kayo magpaliwanag Dami ko natutunan sa mga video mo💪
Good day,,sir saan nyo Po kinuha Ang multiplier mo 12 sa cemento..tnx po interesting Po Kasi Ang way Ng stimate mo na by volume ..tnx Po..
Detalyado at madaling ang paliwanag mo Engr . Thank you very much sayo .
May pinagkaiba ba yung palitada ng nasa ground floor at sa 2nd floor, mas tumataas ba yung palitada sa exterior (labas) pag pataas ng pataas yung pinapalitadahan? Sa loob kasi negligeable yung safety factor.
Salamat po
Pinakagaling na pag paunawa sir .saludo ako bilang isang mang gagawa. Sana maka pag blog kayo tongkol sa asintada labir cost using chb#4 sir. Salamat
Ok po soon
Engr. ano po ba ang output ninyo sa 100 pesos per sqm. ? Rough finish po ba o smooth finish (with pure cement)
sir yong 1.08x12 saan nyo po kinuha ang #12? or para saan yong #12? nalito kasi ako don 😊 thanks po
Hahahah ser.. grabi nmn yang 105 per square meter mo.. mason din ako. Yung square meter mo
Parang arawan din... may kasabihan ser iba ang galawan sa arawan at per square meter ser... salute sana ako sa pag palinawag mo ang problema lugi kaming mga mason sa ganyan na sestema pa pag palitada dito nga probinsya 180 na yung sagad na square meter. Ano pa kaya sa manila..
Walang maraming factor yan at ung amount is based sa nagawa at that particular day. That is merely base on actual investigation and no other meaning to forget all other factors that may affect the contract price of every contractor. Anyway thanks for watching po.
Super helpful ng videos nyo. Ang galing nyo po ninyong guro. ❣️☺️
salamat po sa idea sir. nakakatulong po ang ganito sa gaya ko na. wala talaga idea sa cost budgeting sa pagpapagawa ng bahay ,kasalukuyan po kc ,pinapalitadahan ko maliit kung bahay,kaya nanood po ako ng paliwanag mo sir..salamat po🙏 God bless
Sir ano po ba ung brand ng semento ang maganda para sa plastering? At anong brand ng semento naman ang maganda para sa flooring? Sana po masagot 😊😊god bless you more kuya ed
Good day! Sir, magtatanong lang sana ako kong pwede malaman sa inyo. Magkano aabutin sa pag extension ng bahay kong ang sukat ay 3m x 5m. Ang taas ay kwarto at ang baba ay kusina/ Dining. 4 na poste at slabs po.
Idol saan nakuha ung x12 at x1 na multiplier sa 1.08? Just want to understand
Thank you sir gabs !!
Have a great day po
Anggaling po sir may natutuhan ako
Boss nasubukan mo n b yong 3d panel SRC panel kc parang gusto ko cya kaysa CHB
Very informative.!! 👍👍👍
Sir di po klaro pano na compute yung buhangin paki explain po ng computation
Maraming salamat sir sa panibago nyong topics ng construction works pertaining sa estimation ng plastering works.
Pero may minor comment lang ako sir sa material na sand dahil exactly 1 lang kasi ang multiplier mo sa volume ng plastering area po, mas the best po sana kong 1.2 or 1.25 ng volume of plastering area yong sand para hindi mag under yield yong mixture po.
Thanks po, ung sand ok for 1.2 since minsan ang buhangin maraming coarse aggregate. Or use the maximum possible thickness
@@GabsRomano sir puwede ba hindi lagyan ng tie beam ang dalawang palapag na bahay 6x8 na bahay
San po kinuha yun 12 savpagkuha kung ilan cement magamit
Ayos👍
san nakuha sir un 12 na minultiply sa 1.08 at un 1
Alin po ba sir ang mahal ang presyo ung plustering sa wall or ung mga kantohan like window or door?tnx po
Naka subscribe na po ako sir sana po tutorial naman po paano mag estimate ng magagamit na cemento at buhangin at adhesive na magagamit sa drypack pang tiles yung room area po is 60sqm. At thickness ng mortar is 2inch sslamat po sana masagot👏👏👏👏
Paano mag estimate ng mortar ng filling sa chb at magkano Ang labor?
linear meter ang mga corner sir..
Ang usapan usapan regardless of the factors na sinasabi mo. Mas maganda pa rin pakyawan sa labor. Yung me Ari na Ang bahala sa materials. Para isang presyohan na lng. Magulo Yan, madaming additional charges dahil sa mga factors
Tama po talaga kayo Jan sir.
Salamat po
Sir yong buhangin na gagamitin kailangan pang bistayin
Yung karpintero ko po 1k per block singil niya sa akin lugi po ba yan ako?? Sir
Ayos
sir kasama ba ang pag aayag ng buhangin sa kontrata ng palitada? thank you
Good day. Engr. Maraming salamat sa mga video MO... Very informative... Ask ko Lang Kung may takdang layo ang septic tank sa foundation NG post NG bahay... At maari bang nasa loob NG septic tank Yun is ang part NG foundation NG poste NG bahay... Salamat po sa pagtugon.. God bless
Walang required distance as long as di nakaka apekto sa pundasyon
,.samin dato Mindanao,.120 per square meter para sa walling,.180 per meter Ang mga kantohan,.
Sir. Tanung kung po. Kung magkano. Ang pakyaw per. Cr. Common Cr po sir.
Ilan hollowblock po ang taas nyan
150 or 120 square meter po
Sir hm po palitada at pintura. total 120 sqm na pader, gilid at harap kasama po mga biga. Ang sinisingil po is 45k. Mahal po ba?
Mahal po pero check nio rin po bka maraming design or kantuhan.
Arch. Pls paano mag estimate magpapinta
Mora nman yung sand boss
Sir ask ko lng po anu maganda pang mix sa palitada para d magcrack, at anung maganda mix din sa pang firewall para d tumagas ulan. God bless
Usually class b ok na mixture para sa palitada, pinakamaganda na ma maintain ang thickness sa lahat ng area para consistent ang tamang kapal ng palitada. Kung firewall lagyan nalang ng sahara para kahit paano may anti leak.
pag firewall pwede na lagyan ng SAHARA para yung basic weather protection meron ito. pero ako pinapa-apply ko ang ThoroSeal.
sir un pagkain ng worker kasama ba sa per day na php 115
My marecomend ba kayo na tao para mag finish ng bahay sana namin?
lumalabas na 6 sq/m per day ang productivity ng bawat isang labor. Mabilis o mabagal?
bawat isang oras ay kaya nilang magtapos ng about .8 sqm per hour!
8 SQM per hour????? Lupeeeettt mo ah
Analyze pls. And check if there is decimal in the comment!
.8 square meter so sa isang araw ay 6.4 square meter
sir, pwde po ba makahingi ng sample by division/
BOQ with price (all disciplines) at excel soft copy. tnx po in advance.
kaya hindi lagi applicable yung percentage basis sa labor. tulad nito mas mataas pa labor cost kaysa material cost.
Sir nagpapapalitada ako n bahay taas lang mura ba yngg 30k per pader na bayad?
Ok yan dahil bakod.paano naman yung nasa second and 3rd floor tapos sa labas pa.wla kayong makukuha na ganyan kamura.
True, for very accessible area ang low height na di kailangan ng scaffolding assembly.
Following
Kailangan itama sa hulog ,tatasian yan ,dikami nagawa ng walang tansi ,kasi kailangan tama sa julog ang finish
Senaonapayan ser 150,na ngayon
Mahihirapan po ang labor pag magisa lang cia
kya nmn nag k cruck kc minadali ang pag bara
Hello po, ask ko lang po if nagpaslab po. 3days after pwede na po ba magpaasinta? Pero di po nila aalisin ung mga porma. Habang nagpapatuyo nag aasinta na po sila, ok lang ba un? Salamat po
Sir bakit may nakausap kami about sa slab kung magkano per sqm sabi 12k daw
Wow more than 50% of total contract in a typical residential project!
Sinauna payang 105 boss
Pwede parin sa favourable conditions ng site.
Taga davao ka sir?
No sir
Mahina Po Ang audio nyo
Para yatang Hindi mo natumbok sa vlog mo ang presenteng presyo tungkol sa kalakalan sa pagpapalitada, kung magkano nga ba ngayon ang singilan,parang binibigyan mo nang diskusyon ang mason na gumagawa at ang nagpapagawa sa singilan nang pagpapalitada sa tunay na presyuhan ngayon....namimislead mo yong magpapagawa Ng pagpapalitada sa tunay napresyuhan nito
E2 po ay malapit sa tinatawag na backward computation or malapit sa presyo ng mismong owner or nagpapagawa.
Malinaw sir salamat
Iba yong arawan kay sa cuntrata.. oo enginer ka piro kami ang nakka alam kong kaylan nami matapos
Sana po gawa ka ng channel at susuportahan kta kc madami ka pong kaalaman. Share it nalang para maging good vibes ang tono mo.
Iba talaga arawan sa contrata...kung arawan matatapos ng 1 linggo...kung contrata matagal na 1 araw diba?
kikita kayo yong trabahador halos mamatay katatrabaho ganyan bayad nyo
Yan po ay actual computation ng owner at base sa payroll for several days.
mura nman ng bayad nyo patay ang trabahador walang magtitiyaga sa ganyan
Sa estimate maaaring tumaas, malas kung under estimate pero meron din tayong backward computation
Kadalasan nandadaya ang mga labor.. tsk
Di po maiiwasan
Sir mura kung P115/square mtrs. sa estimate niyo..
...dito sa Amin 200 per square mtrs.pakyawan tapos pagkatapos gawin ilang araw may bitak bitak na😡🤬... Pag-arawan naman naguubos Oras sa paghuhulog at paglalagay pisi parang pinupulido pero pagkatapos tabingi parin naman 😡🤬.. lugi nagpapagawa😤😤...
200 for 1 mason with 1 laborer
@@GabsRomano sir depende kung ilan sila gagawa depende sa luwang nung area... Pero madalas pares lang 1mason 1helper kung maliit na bahay .basta 200 -250 pa nga per square meter ang pakyaw nila depende pa kung maganda yung hulog asinta ng CHB...
1.08m^3 ang volume ng palitada pero yung sand 1.08^3 ang volume?!? LOL
e yung volume pa ng cement madadagdag pa sa 1.08m^3 ng sand so sobra2x na yan! LMAO
base sa quantity ng materials mo eto ang volume ng kada isa.
volume ng sand 1.08m^3
volume ng 12.96 bags cement is 0.36m^3
volume ng water is 0.18m^3
total volume = volume sand + volume cement + volume water
total volume = 1.08 + 0.36 + 0.18 = 1.62m^3
bale 1.62m^3 na ang total volume of materials mo pero ang kailangan mo is 1.08m^3 lang or 50% over ka na!! LMAO
Wow you are great. I will appreciate if you create a channel para naman maibahagi mo expertise mo po. I am counting on that po
Please study the concept of mix proportion of course aggregates up to finest aggregate. Salamat po
@@GabsRomanomay umeepal engineer