European Spallation Source
European Spallation Source
  • 75
  • 74 138
ESS Highlights - Q2 2024
In the second quarter of 2024, ESS made significant progress in the installation, testing and commissioning of the facility, continuing the journey on the #RoadToScience.
Watch this video for a summary of the achievements made from April to June 2024.
Переглядів: 1 327

Відео

Moderator cap installation
Переглядів 2133 місяці тому
22 May 2024: Installation of the moderator cap, a key component to seal the ESS Target vacuum vessel, hosting the equipment for neutron equipment.
Q1 2024 highlights video
Переглядів 9224 місяці тому
In the first quarter of 2024, ESS made significant progress in preparing the Accelerator for the 'Beam on Dump' milestone set for November. This involves the commissioning of all technical components and operating the accelerator to the beam dump, ensuring readiness for the next big objective of Beam on Target and neutron production. This video is a summary of the progress made in January to Ma...
Accelerate Your Teaching MOOC Module 1 Introduction to Scientist Stories
Переглядів 705 місяців тому
Christine Darve, Engineering Scientist at ESS, introduces this set of short videos of different people who use accelerators in their job or research. The videos are 5 minutes long and are suitable for using in science lessons as a way to introduce particle accelerators, STEM careers and research using Big Science, into your teaching. This film was produced with funding from the EU as part of th...
ESS Highlights 2023
Переглядів 2 тис.8 місяців тому
A summary of the progress made on ESS Road To Science in 2023, with focus on the Accelerator, Target Station and Instruments.
The heart of ESS - installation of the Target Wheel and Moderator
Переглядів 2,8 тис.9 місяців тому
In November 2023, ESS achieved a major milestone in installing the Target Wheel and Moderator Reflector Plug, key components for the neutron production at the facility. This movie shows the installation with commentary and explanations on how it works and why it is important, presented by ESS staff and In-Kind Partners. In-Kind Partner for the Target Wheel: ESS Bilbao, Spain. In-Kind Partner fo...
ESS Target Wheel 1,000 hours test spin completed
Переглядів 32310 місяців тому
See the last seconds of the Target Wheel rotation tests in the on-site Target Test Stand, as 1,000 hours of seamless spinning is completed. The final handling and rotation tests of the Target Wheel, shaft and drive unit with the helium rotary unit - all delivered from Spanish In-Kind Partner ESS Bilbao - paves the way for final installation of the wheel and shaft into the ESS Target Monolith ve...
Who inspires you?
Переглядів 2 тис.10 місяців тому
Short interviews with the speakers from the Accelerate Your Teaching MOOC: - Prof. Carsten Welsch, University of Liverpool, UK - Prof. Phill Manning, University of Manchester, UK - Dr Zoë Fisher, European Spallation Source, Sweden - PhD student Kristine Krighaar, University of Copenhagen, Denmark This is one of a series of short films made for high school science teachers and students. They wer...
Superconductors and data
Переглядів 60711 місяців тому
Speaker: Kristine Krighaar, University of Copenhagen, Denmark All large facilities use and produce huge quantities of data, both to monitor and control the machine and all the scientific data that is produced in the experiments. Kristine’s research is on the science of superconductors and she uses simulated data to anticipate what experimental data she will get once the ESS is switched on and g...
Accelerators for life sciences
Переглядів 66211 місяців тому
Speaker - Dr Zoë Fisher, European Spallation Source, Sweden Biology and the life science use neutrons and x-rays in complementarity to help decipher the relationship between the structure and function of many molecules, such as proteins and enzymes. This can even help to create medicines to treat many diseases such as cancer. This is one of a series of short films made for high school science t...
Accelerators for particles and the cosmos
Переглядів 1,1 тис.11 місяців тому
Speaker - Professor Carsten Welsch, University of Liverpool, UK Theme: How scientists use particle Accelerators to understand the origins of the Universe and the smallest building blocks of matter. This is one of a series of short films made for high school science teachers and students. They were produced by the production company Making Science the Star, with colleagues from ESS, and with fin...
Accelerators to study the distant past
Переглядів 1 тис.11 місяців тому
Speaker - Professor Phil Manning, University of Manchester, UK Theme: Using light to reveal the secrets of fossils and dinosaurs. This is one of a series of short films made for high school science teachers and students. They were produced by the production company Making Science the Star, with colleagues from ESS, and with financial support from the EU from an ERASMUS project called Accelerati...
What is ESS?
Переглядів 5 тис.Рік тому
A short video explaining what the European Spallation Source (ESS) is, how it works and what it is for.
Installation of cryomodules in the ESS Superconducting Linac.
Переглядів 475Рік тому
Short video showing the installation of double-cavity cryomodules in the spoke section of the ESS Accelerator.
ESS Highlights from the first half of 2023
Переглядів 1 тис.Рік тому
This video gives an overview of the achievements so far in 2023 in the quest to construct and install the ESS facility. It also provides a glimpse into the future, listing activities coming up in the second part of 2023.
Beam Commissioning at ESS
Переглядів 515Рік тому
Beam Commissioning at ESS
The last Neutron Beam Port Insert installed at ESS
Переглядів 344Рік тому
The last Neutron Beam Port Insert installed at ESS
Permanent Shielding for Target Monolith Vessel Completed
Переглядів 317Рік тому
Permanent Shielding for Target Monolith Vessel Completed
ESS Ceremony - celebrating the achievement of major project milestones in Accelerator and Target.
Переглядів 370Рік тому
ESS Ceremony - celebrating the achievement of major project milestones in Accelerator and Target.
Target Monitoring Plug - test installation
Переглядів 229Рік тому
Target Monitoring Plug - test installation
Target wheel - the heart of ESS
Переглядів 920Рік тому
Target wheel - the heart of ESS
Moderator test installation
Переглядів 181Рік тому
Moderator test installation
Nanocosmic Investigations - Artists in Conversation with ESS
Переглядів 288Рік тому
Nanocosmic Investigations - Artists in Conversation with ESS
Cryomodule installation starts at ESS
Переглядів 470Рік тому
Cryomodule installation starts at ESS
UK in-kind contributions to the ESS project
Переглядів 387Рік тому
UK in-kind contributions to the ESS project
Join Sweden - ESS for Life Science
Переглядів 291Рік тому
Join Sweden - ESS for Life Science
Neutron Beam Port Plug installation at ESS
Переглядів 942Рік тому
Neutron Beam Port Plug installation at ESS
Double pancake to Monolith vessel
Переглядів 255Рік тому
Double pancake to Monolith vessel
Particle-free installation at ESS
Переглядів 120Рік тому
Particle-free installation at ESS
Cryomodule coupler exchange at ESS
Переглядів 435Рік тому
Cryomodule coupler exchange at ESS